11448 W WATERFORD ST 90049
Certificate Information: 11448 W WATERFORD ST 90049
- Application / Permit
- 21010-30000-05940
- Plan Check / Job No.
- B21WL05006
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (n) 1-story ADU per state code
- Permit Issued
- Issued on 4/18/2022
- Issuing Office
- Current Status
- CofO Issued on 6/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2021 | TARIK SAOUD |
| Corrections Issued | 11/30/2021 | TARIK SAOUD |
| Quality Review Completed | 12/6/2021 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| Applicant returned to address corrections | 3/23/2022 | TARIK SAOUD |
| Plan Check Approved | 4/12/2022 | TARIK SAOUD |
| Issued | 4/18/2022 | APPLICANT |
| CofO in Progress | 6/12/2023 | MICHAEL PELHAM |
| Permit Finaled | 6/13/2023 | DANIEL ORRANTE |
| CofO Issued | 6/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/20/2021 | EDUARDO HERMOSO |
| Sewer availability | Cleared | 1/5/2022 | TRACY TATE |
| Low Impact Development | Cleared | 2/15/2022 | TA ANH |
| Trees in Parkway | Cleared | 2/18/2022 | ADALBERTO VERA |
| Permit | Cleared | 3/23/2022 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 3/23/2022 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | TRACY TATE |
| Address approval | Cleared | 4/1/2022 | TRACY TATE |
| Grading Pre-Inspection | Cleared | 4/12/2022 | TARIK SAOUD |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/10/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/31/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 5/31/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 6/6/2022 | Approved | BRENDAN LOONEY |
| METHANE-Rough | 6/14/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Methane Barrier | 7/13/2022 | Approved | CARLOS MATAMOROS |
| METHANE-Barrier | 7/15/2022 | Approved | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 9/23/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 10/4/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/4/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 10/6/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Approved | CARLOS MATAMOROS |
| METHANE-Rough | 10/13/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Methane Barrier | 10/14/2022 | Conditional Approval | CARLOS MATAMOROS |
| METHANE-Final | 10/18/2022 | Approved | CARLOS MATAMOROS |
| Shower Pan | 10/18/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 10/25/2022 | Approved | CARLOS MATAMOROS |
| MERV13>=Rough | 10/25/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 10/25/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/16/2022 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 2/21/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 2/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 2/21/2023 | Approved | STEPHANIE SWANSON |
| Insulation | 2/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/21/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/27/2023 | Approved | CARLOS MATAMOROS |
| Gas Test | 4/27/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 4/27/2023 | Approved | CARLOS MATAMOROS |
| Final | 6/7/2023 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/7/2023 | Approved | CARLOS MATAMOROS |
| Green Building Final | 6/7/2023 | No Access for Inspection | CARLOS MATAMOROS |
| MERV13>=Final | 6/7/2023 | Approved | CARLOS MATAMOROS |
| METHANE-Subgrade | 6/7/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 6/7/2023 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 6/7/2023 | Approved | CARLOS MATAMOROS |
| Final | 6/9/2023 | Partial Approval | CARLOS MATAMOROS |
| Green Building Final | 6/9/2023 | Approved | CARLOS MATAMOROS |