6413 1/2 W 6TH ST 90048
Certificate Information: 6413 1/2 W 6TH ST 90048
- Application / Permit
- 21010-30000-05917
- Plan Check / Job No.
- B21WL04989
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story ADU at rear of the lot per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 12/7/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 12/16/2021 | TARIK SAOUD |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| Applicant returned to address corrections | 5/2/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 7/27/2023 | REZA HAGHIGHAT |
| Issued | 10/20/2023 | APPLICANT |
| CofO in Progress | 10/2/2025 | EVAN COOPER |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
| CofO Issued | 10/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| CPC | Cleared | 7/20/2022 | ASHLEY RODARTE |
| Address approval | Cleared | 8/1/2022 | WALLIE JONG |
| Construction within easement | Cleared | 8/8/2022 | TINA MIRANDA |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 10/19/2022 | STEVE MELGAR |
| Trees in Parkway | Cleared | 7/6/2023 | FELIPE HERNANDEZ |
| Low Impact Development | Cleared | 7/10/2023 | TOMMY YIN |
| Permit | Cleared | 7/13/2023 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 7/13/2023 | WALLIE JONG |
Contact Information
| Contractor | Intrepid Builders Inc; Lic. No.: 1063638-B | 1420 NORTH SIERRA BONITA #408 LOS ANGELES, CA 90046 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/29/2023 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/13/2023 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 12/29/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/29/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| METHANE-Barrier | 12/29/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| METHANE-Subgrade | 12/29/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 1/2/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/4/2024 | Conditional Approval | JESUS RODRIGUEZ |
| METHANE-Barrier | 1/4/2024 | Approved | JESUS RODRIGUEZ |
| METHANE-Subgrade | 1/4/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Partial Approval | MEL KHACHATOURIAN |
| Wood Frame | 2/28/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 2/29/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 3/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 3/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 3/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 4/5/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 4/5/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 4/5/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 4/5/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 4/19/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 4/19/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 4/19/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 4/19/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 4/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 4/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 4/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 4/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Wood Construction | 4/24/2024 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 4/29/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 4/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 4/29/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 4/29/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 5/7/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/10/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 5/10/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 5/10/2024 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 5/10/2024 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 5/10/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 5/28/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 6/3/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 9/23/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 10/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| Final | 10/21/2024 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Final | 10/21/2024 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Final | 11/13/2024 | Approved | MEL KHACHATOURIAN |
| Final | 4/18/2025 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 4/18/2025 | Approved | EVAN COOPER |
| Green Building Final | 4/18/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 4/18/2025 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 4/18/2025 | Approved | EVAN COOPER |
| Final | 10/2/2025 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 10/2/2025 | Approved | EVAN COOPER |