1553 W 214TH ST 90501
Certificate Information: 1553 W 214TH ST 90501
- Application / Permit
- 21010-30000-05890
- Plan Check / Job No.
- B21WL04976
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New garage with ADU unit above per ordinance LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | HOOMAN HAJIZADEH |
| Corrections Issued | 12/16/2021 | HOOMAN HAJIZADEH |
| Quality Review Completed | 12/27/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 2/22/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 3/16/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 3/22/2022 | HOOMAN HAJIZADEH |
| Plan Check Approved | 4/19/2022 | HOOMAN HAJIZADEH |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| Issued | 7/13/2022 | APPLICANT |
| CofO in Progress | 5/11/2026 | JOSEPH MCGARRY |
| Permit Finaled | 5/11/2026 | ANSON MAGLASANG |
| CofO Issued | 5/11/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/11/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2022 | ERIK BEASLEY |
| Disturb/Remove Protected Trees | Cleared | 1/21/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 2/8/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 2/8/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 4/5/2022 | JOSE HERNANDEZ |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/18/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/24/2023 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 1/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/24/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/13/2023 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 3/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 4/5/2023 | Approved | EUGENE CASSIDY |
| Gas Test | 8/1/2023 | Approved | JAMES CHAVEZ |
| Insulation | 8/1/2023 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 8/1/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 9/11/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 10/25/2023 | Approved | EUGENE CASSIDY |
| Insulation | 11/7/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 11/17/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 12/22/2023 | Approved | EUGENE CASSIDY |
| Sewer | 6/27/2024 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 8/14/2024 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 8/29/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/4/2024 | Approved | EUGENE CASSIDY |
| Sewer | 11/6/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/29/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/24/2025 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 9/24/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 9/24/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/1/2025 | Approved | EUGENE CASSIDY |
| Final | 10/1/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/1/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 10/1/2025 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 10/1/2025 | Approved | EUGENE CASSIDY |
| Final | 2/19/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 3/19/2026 | Corrections Issued | EUGENE CASSIDY |
| Final | 5/5/2026 | OK to Issue CofO | JOSEPH MCGARRY |