537 N FORMOSA AVE 90036
Certificate Information: 537 N FORMOSA AVE 90036
- Application / Permit
- 21010-30000-05876
- Plan Check / Job No.
- B21WL04954
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- new detached ADU unit and attached 2-car garage
- Permit Issued
- Issued on 6/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | TARIK SAOUD |
| Corrections Issued | 11/23/2021 | TARIK SAOUD |
| Quality Review Completed | 12/6/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 4/20/2022 | TARIK SAOUD |
| Plan Check Approved | 6/10/2022 | TARIK SAOUD |
| Issued | 6/13/2022 | APPLICANT |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| CofO in Progress | 1/20/2023 | MICHAEL LEWIS |
| Permit Finaled | 1/26/2023 | DEROLD HAUFF |
| CofO Issued | 1/26/2023 | DEROLD HAUFF |
| Permit Finaled | 1/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2022 | JEANIE LAM |
| Permit | Cleared | 2/1/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2022 | JEANIE LAM |
| Sewer availability | Cleared | 2/2/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 4/5/2022 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 4/27/2022 | CINDY JOSSELYN |
| Roof/Waste drainage to street | Cleared | 4/27/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 4/28/2022 | RIDWAN HARDY |
| Trees in Parkway | Cleared | 5/10/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Bhfc Inc; Lic. No.: 553541-B | 9701 WEST PICO BOULEVARD # 209 LOS ANGELES, CA 90035 |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: C84559 | 9163 LEROY STREET SAN GABRIEL, CA 91775 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Pre-Inspection | 6/15/2022 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 7/5/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 7/5/2022 | Partial Approval | JOSEPH MCGARRY |
| METHANE-Barrier | 7/5/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/5/2022 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 7/5/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 7/6/2022 | Not Ready for Inspection | ADAM ESCOTO |
| METHANE-Rough | 7/15/2022 | Approved | ALIZAH MAYAGOITIA |
| Deputy Methane Barrier | 7/19/2022 | Conditional Approval | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 7/25/2022 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 9/6/2022 | Approved | MICHAEL LEWIS |
| Sewer | 9/6/2022 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 9/12/2022 | Conditional Approval | MICHAEL LEWIS |
| Rough-Elec/Plmb/HVAC | 9/19/2022 | Approved | MICHAEL LEWIS |
| Shower Pan | 9/19/2022 | Approved | MICHAEL LEWIS |
| Wood Frame | 9/22/2022 | Approved | MICHAEL LEWIS |
| Insulation | 9/28/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/28/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 10/3/2022 | Partial Inspection | MICHAEL LEWIS |
| Gas Test | 10/28/2022 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 10/28/2022 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 11/29/2022 | Not Ready for Inspection | MICHAEL LEWIS |
| HVAC-Final | 11/29/2022 | Conditional Approval | MICHAEL LEWIS |
| PLUMBING-Final | 11/29/2022 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/15/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 12/22/2022 | Not Ready for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/5/2023 | Approved | MICHAEL LEWIS |
| Final | 1/5/2023 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 1/5/2023 | Approved | MICHAEL LEWIS |
| Gas Test | 1/5/2023 | Approved | MICHAEL LEWIS |
| Green Building Final | 1/5/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 1/5/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 1/5/2023 | Approved | MICHAEL LEWIS |
| METHANE-Barrier | 1/5/2023 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 1/5/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 1/5/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 1/5/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 1/5/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 1/5/2023 | Approved | MICHAEL LEWIS |
| Final | 1/19/2023 | OK to Issue CofO | MICHAEL LEWIS |