179 S ROCKINGHAM AVE 90049
Certificate Information: 179 S ROCKINGHAM AVE 90049
- Application / Permit
- 21010-30000-05854
- Plan Check / Job No.
- B21WL04939
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- (N) DEATCHED STORAGE BUILDING WITH OUTDOOR FIRE PLACE AT REAR OF THE LOT
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 11/14/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 4/7/2022 | JASON JANGADA |
| Applicant returned to address corrections | 5/20/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| Applicant returned to address corrections | 6/16/2022 | DAVID CASTILLO |
| Plan Check Approved | 7/28/2022 | DAVID CASTILLO |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 10/18/2024 | JESUS RODRIGUEZ |
| CofO Issued | 10/30/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/30/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/29/2022 | STEVEN JIN |
| Miscellaneous | Cleared | 1/31/2022 | DALIA MOKAYED |
| Hydrant and Access approval | Cleared | 3/11/2022 | LARRY REDDEN |
| Grading Pre-Inspection | Cleared | 4/7/2022 | JAHANSHAH POURHASSAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2022 | STEVEN JIN |
Contact Information
| Contractor | J R C Group Inc; Lic. No.: 980658-B | 8981 SUNSET BLVD STE 505 LOS ANGELES, CA 90069 |
| Engineer | Lau,, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/3/2022 | Partial Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/28/2023 | Partial Inspection | OGANES TARAKHCHYAN |
| Grading Pre-Inspection | 3/28/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 4/4/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 4/10/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 4/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/9/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/9/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/12/2023 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 5/26/2023 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 8/31/2023 | Approved | KEVIN SARGSYAN |
| Deputy Steel/Welding | 9/29/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 10/5/2023 | No Access for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 10/11/2023 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2023 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 10/11/2023 | Corrections Issued | KEVIN SARGSYAN |
| Masonry Wall/Backfill | 1/9/2024 | Corrections Issued | ARAM AVEDISIAN |
| Masonry Wall/Backfill | 1/10/2024 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 5/17/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/4/2024 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/4/2024 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/9/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Drywall Nailing | 9/9/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/9/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Final | 9/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 9/9/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/9/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/9/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 9/9/2024 | Not Required | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 9/9/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/4/2024 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 10/4/2024 | Approved | JESUS RODRIGUEZ |
| Final | 10/4/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/4/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/18/2024 | Approved | JESUS RODRIGUEZ |
| Final | 10/18/2024 | OK to Issue CofO | JESUS RODRIGUEZ |