3232 S CLUB DR 90064

Certificate Information: 3232 S CLUB DR 90064

Application / Permit
21010-30000-05816
Plan Check / Job No.
B21WL04923
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SFD w./ att. garage
Permit Issued
Issued on 12/20/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 TARIK SAOUD
Corrections Issued 11/23/2021 TARIK SAOUD
Quality Review Completed 12/6/2021 CHIHARU SUZUKI
Building Plans Picked Up 12/7/2021 APPLICANT
Plan Check Approved 12/7/2022 REZA HAGHIGHAT
Issued 12/20/2022 APPLICANT
CofO in Progress 10/16/2025 ANDREW NAVE
Permit Finaled 10/16/2025 RICHARD STEINBACH
CofO Issued 10/16/2025 RICHARD STEINBACH
Permit Finaled 10/16/2025 RICHARD STEINBACH

Permit Application Clearance Information

Trees in Parkway Cleared 12/29/2021 ADALBERTO VERA
Eng Process Fee Ord 176,300 Cleared 1/4/2022 KATHLEEN LEE
Sewer availability Cleared 1/4/2022 KATHLEEN LEE
Hydrant and Access approval Cleared 2/15/2022 JOHN CONNEALLY
Specific Plan Cleared 3/16/2022 EDUARDO HERMOSO
Low Impact Development Cleared 5/15/2022 SUNG JOON WON
Permit Cleared 5/16/2022 KATHLEEN LEE
Roof/Waste drainage to street Cleared 5/16/2022 KATHLEEN LEE
Grading Pre-Inspection Cleared 12/7/2022 TARIK SAOUD

Contact Information

Architect Blumenberg,, Richard Leo; Lic. No.: C10862 15200 SUNSET BLVD STE 201      PACIFIC PALISADES, CA 90272
Contractor Owner-Builder       ,
Engineer Bains,, Gagan Prit Singh; Lic. No.: S4482 222 E HUNTINGTON DR STE 235      MONROVIA, CA 91016

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/26/2023 Approved CLAYTON GRAHAM
Underground Mechanical 4/26/2023 Partial Approval CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 5/9/2023 Partial Approval CLAYTON GRAHAM
Footing/Foundation/Slab 5/31/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 10/16/2023 Corrections Issued CLAYTON GRAHAM
Deputy Wood Construction 12/13/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/13/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/13/2023 Approved OGANES TARAKHCHYAN
Underground Mechanical 12/13/2023 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 12/14/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/11/2024 Partial Approval JESUS PINEDA
Green Building Rough 1/11/2024 Not Ready for Inspection JESUS PINEDA
Verify Sprinkler Sign Off 1/11/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 1/31/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Rough 1/31/2024 Approved OGANES TARAKHCHYAN
Wood Frame 2/1/2024 Approved OGANES TARAKHCHYAN
Insulation 3/20/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/5/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/5/2024 Approved OGANES TARAKHCHYAN
Shower Pan 4/5/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/11/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 9/15/2025 Approved MEL KHACHATOURIAN
Gas Test 9/15/2025 Approved MEL KHACHATOURIAN
PLUMBING-Final 9/15/2025 Approved MEL KHACHATOURIAN
Service/Power Release 9/15/2025 Not Ready for Inspection MEL KHACHATOURIAN
Deputy Reinf. Concrete 9/17/2025 Conditional Approval ASHLEY THOMPSON
Service/Power Release 9/17/2025 Approved MICHAEL PELHAM
Final 10/9/2025 Corrections Issued EVAN COOPER
Green Building Final 10/9/2025 Approved EVAN COOPER
HVAC-Final 10/9/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 10/9/2025 Approved EVAN COOPER
Final 10/16/2025 OK to Issue CofO ANDREW NAVE