1991 N ALEXANDRIA AVE 90027
Certificate Information: 1991 N ALEXANDRIA AVE 90027
- Application / Permit
- 21010-30000-05762
- Plan Check / Job No.
- B21WL04857
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 2-story S.F.D. w/ 2-car garage
- Permit Issued
- Issued on 9/9/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 11/3/2021 | APPLICANT |
Assigned to Plan Check Engineer | 11/12/2021 | TARIK SAOUD |
Corrections Issued | 11/16/2021 | TARIK SAOUD |
Quality Review Completed | 11/18/2021 | CHIHARU SUZUKI |
Applicant returned to address corrections | 3/7/2022 | TARIK SAOUD |
Applicant returned to address corrections | 4/1/2022 | TARIK SAOUD |
Applicant returned to address corrections | 5/5/2022 | TARIK SAOUD |
Applicant returned to address corrections | 7/22/2022 | TARIK SAOUD |
Plan Check Approved | 8/23/2022 | TARIK SAOUD |
Building Plans Picked Up | 8/23/2022 | APPLICANT |
Issued | 9/9/2022 | APPLICANT |
CofO in Progress | 4/22/2024 | ENRIQUE MIRELES |
CofO Issued | 4/29/2024 | DEROLD HAUFF |
Permit Finaled | 4/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
Trees in Parkway | Cleared | 12/21/2021 | ADALBERTO VERA |
Low Impact Development | Cleared | 1/27/2022 | JONATAN VELASQUEZ |
BHO/Hillside ordinance | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
BHO/Hillside ordinance | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
BHO/Hillside ordinance | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
BHO/Hillside ordinance | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
BHO/Hillside ordinance | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
Eng Process Fee Ord 176,300 | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
Permit | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
Roof/Waste drainage to street | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
Sewer availability | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
City Hist. Cultural Monument | Cleared | 2/10/2022 | LAMBERT GIESSINGER |
Historic monument | Cleared | 2/10/2022 | LAMBERT GIESSINGER |
Hydrant and Access approval | Cleared | 2/18/2022 | DWAYNE LAURENT |
Grading Pre-Inspection | Cleared | 8/23/2022 | TARIK SAOUD |
Miscellaneous | Cleared | 8/23/2022 | TARIK SAOUD |
Contact Information
Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 4/20/2023 | Approved | JOSEPH MCGARRY |
Special/Order Compliance | 4/20/2023 | Corrections Issued | JOSEPH MCGARRY |
Deputy Reinf. Concrete | 5/25/2023 | Partial Approval | JOSEPH MCGARRY |
Deputy Grading | 6/1/2023 | Approved | JOSEPH MCGARRY |
Deputy Grading | 6/1/2023 | Partial Approval | JOSEPH MCGARRY |
Deputy Reinf. Concrete | 6/1/2023 | Partial Approval | JOSEPH MCGARRY |
Deputy Reinf. Concrete | 6/2/2023 | Partial Approval | JOSEPH MCGARRY |
Deputy Grading | 6/6/2023 | Partial Approval | JOSEPH MCGARRY |
Deputy Reinf. Concrete | 6/6/2023 | Partial Approval | JOSEPH MCGARRY |
Deputy Reinf. Concrete | 6/12/2023 | Partial Approval | JEFFREY MEAD |
Deputy Reinf. Concrete | 7/6/2023 | Approved | JOSEPH MCGARRY |
Footing/Foundation/Slab | 7/6/2023 | Partial Approval | JOSEPH MCGARRY |
Excavation/Setback/Form/Re-Bar | 7/17/2023 | Partial Approval | JOSEPH MCGARRY |
Footing/Foundation/Slab | 7/17/2023 | Partial Approval | JOSEPH MCGARRY |
Deputy Reinf. Concrete | 7/19/2023 | Partial Approval | JOSEPH MCGARRY |
Deputy Reinf. Concrete | 7/24/2023 | Partial Approval | JOSEPH MCGARRY |
Footing/Foundation/Slab | 8/25/2023 | Not Ready for Inspection | JEFFREY MEAD |
PLUMBING-Rough | 8/25/2023 | Not Ready for Inspection | JEFFREY MEAD |
Underground Mechanical | 8/25/2023 | Approved | JEFFREY MEAD |
Excavation/Setback/Form/Re-Bar | 8/31/2023 | Approved | JEFFREY MEAD |
Deputy Reinf. Concrete | 9/1/2023 | Partial Approval | JOSH MEISTER |
Deputy Reinf. Concrete | 9/5/2023 | Approved | JOSEPH MCGARRY |
Footing/Foundation/Slab | 9/5/2023 | Conditional Approval | JOSEPH MCGARRY |
Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Partial Approval | RICHARD DOCKUS |
Footing/Foundation/Slab | 9/15/2023 | Approved | RICHARD DOCKUS |
Deputy Reinf. Concrete | 9/19/2023 | Partial Approval | JOSEPH MCGARRY |
Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Approval | JOSEPH MCGARRY |
BUILDING-Rough-Frame | 10/31/2023 | Partial Inspection | JOSEPH MCGARRY |
ELECTRICAL-Rough | 10/31/2023 | Partial Inspection | JOSEPH MCGARRY |
Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
Gas Test | 10/31/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
Green Building Rough | 10/31/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
HVAC-Rough | 10/31/2023 | Corrections Issued | JOSEPH MCGARRY |
Interior/Exterior Lathing | 10/31/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
PLUMBING-Rough | 10/31/2023 | Approved | JOSEPH MCGARRY |
Rough-Elec/Plmb/HVAC | 10/31/2023 | Partial Approval | JOSEPH MCGARRY |
Verify Sprinkler Sign Off | 10/31/2023 | Approved | JOSEPH MCGARRY |
Deputy Wood Construction | 11/1/2023 | Conditional Approval | JOSH MEISTER |
ELECTRICAL-Rough | 11/1/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
ELECTRICAL-Rough | 11/6/2023 | Corrections Issued | JOSEPH MCGARRY |
HVAC-Rough | 11/6/2023 | Conditional Approval | JOSEPH MCGARRY |
BUILDING-Rough-Frame | 11/13/2023 | Conditional Approval | JOSEPH MCGARRY |
ELECTRICAL-Rough | 11/13/2023 | Approved | JOSEPH MCGARRY |
Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Conditional Approval | JOSEPH MCGARRY |
Green Building Rough | 11/13/2023 | Approved | JOSEPH MCGARRY |
Insulation | 11/27/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
Deputy Wood Construction | 11/28/2023 | Partial Approval | JOSEPH MCGARRY |
BUILDING-Rough-Frame | 11/29/2023 | Conditional Approval | JOSEPH MCGARRY |
Insulation | 11/29/2023 | Approved | JOSEPH MCGARRY |
Shower Pan | 11/29/2023 | Approved | JOSEPH MCGARRY |
Drywall Nailing | 12/4/2023 | Conditional Approval | JOSEPH MCGARRY |
Interior/Exterior Lathing | 12/4/2023 | Partial Inspection | JOSEPH MCGARRY |
Shower Pan | 12/4/2023 | Approved | JOSEPH MCGARRY |
ELECTRICAL-Final | 2/20/2024 | Corrections Issued | ENRIQUE MIRELES |
PLUMBING-Final | 2/20/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
PLUMBING-Final | 2/22/2024 | Approved | ENRIQUE MIRELES |
Service/Power Release | 2/22/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
ELECTRICAL-Final | 2/26/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
Green Building Final | 3/7/2024 | Approved | ENRIQUE MIRELES |
HVAC-Final | 3/7/2024 | Corrections Issued | ENRIQUE MIRELES |
SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Not Ready | ENRIQUE MIRELES |
ELECTRICAL-Final | 4/3/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
Final | 4/3/2024 | Corrections Issued | ENRIQUE MIRELES |
PLUMBING-Final | 4/3/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
Service/Power Release | 4/3/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
BUILDING-Rough-Frame | 4/15/2024 | Approved | ENRIQUE MIRELES |
ELECTRICAL-Final | 4/15/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
Final | 4/15/2024 | Corrections Issued | ENRIQUE MIRELES |
HVAC-Final | 4/15/2024 | Approved | ENRIQUE MIRELES |
PLUMBING-Final | 4/15/2024 | Approved | ENRIQUE MIRELES |
SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Approved | ENRIQUE MIRELES |
Service/Power Release | 4/15/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
Smoke Detectors | 4/15/2024 | Approved | ENRIQUE MIRELES |
ELECTRICAL-Final | 4/18/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
HVAC-Final | 4/18/2024 | Approved | JOAQUIN GREENOUGH |
PLUMBING-Final | 4/18/2024 | Approved | JOAQUIN GREENOUGH |
Final | 4/19/2024 | OK to Issue CofO | ENRIQUE MIRELES |
Service/Power Release | 4/19/2024 | Approved | ENRIQUE MIRELES |