262 S JUNE ST 90004
Certificate Information: 262 S JUNE ST 90004
- Application / Permit
- 21010-30000-05734
- Plan Check / Job No.
- B21WL04852
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-Story ADU per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/2/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/2/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2021 | DAVID CASTILLO |
| Corrections Issued | 11/12/2021 | DAVID CASTILLO |
| Quality Review Completed | 11/22/2021 | TARIK SAOUD |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| Applicant returned to address corrections | 1/4/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/26/2023 | DAVID CASTILLO |
| Plan Check Approved | 1/30/2023 | DAVID CASTILLO |
| Issued | 2/2/2023 | APPLICANT |
| Permit Expired-Status Void | 12/9/2024 | AMY COLIN |
| Re-Activate Permit | 4/9/2025 | AMY COLIN |
Permit Application Clearance Information
| Address approval | Cleared | 11/24/2021 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 11/30/2021 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 9/23/2022 | ROGELIO CORTES |
| HPOZ | Cleared | 9/30/2022 | SUKI GERSHENHORN |
| Roof/Waste drainage to street | Cleared | 11/2/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 12/9/2024 | No Access for Inspection | AMY COLIN |
| Pre-Inspection | 6/3/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 6/13/2025 | Corrections Issued | JOSE MACIAS |
| Underground Mechanical | 6/17/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 6/23/2025 | Partial Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/7/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 7/7/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Subgrade | 7/7/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 7/9/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Partial Approval | RONNIE MINDANAO |
| Deputy Wood Construction | 9/4/2025 | Conditional Approval | RONNIE MINDANAO |
| PLUMBING-Rough | 11/13/2025 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/25/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 11/25/2025 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 11/25/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/25/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 11/25/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/4/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 12/4/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Underground Mechanical | 12/4/2025 | Partial Approval | RONNIE MINDANAO |
| HVAC-Rough | 12/30/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 12/30/2025 | Approved | RONNIE MINDANAO |
| Sewer | 12/30/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 12/30/2025 | Approved | RONNIE MINDANAO |
| Rough-Elec/Plmb/HVAC | 1/8/2026 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2026 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 1/20/2026 | Conditional Approval | RONNIE MINDANAO |
| Insulation | 4/6/2026 | Corrections Issued | GEM DE OCAMPO |
| Interior/Exterior Lathing | 4/6/2026 | Corrections Issued | GEM DE OCAMPO |
| Insulation | 4/20/2026 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 4/20/2026 | Corrections Issued | JOSH MEISTER |
| Insulation | 4/23/2026 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 4/23/2026 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 5/20/2026 | Approved | RONNIE MINDANAO |