2206 S GREENFIELD AVE 90064

Certificate Information: 2206 S GREENFIELD AVE 90064

Application / Permit
21010-30000-05685
Plan Check / Job No.
B21WL04811
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story SFD with 2-car garage.
Permit Issued
Issued on 3/30/2022
Issuing Office
Current Status
CofO Issued on 6/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 JAHANSHAH POURHASSAN
Corrections Issued 11/8/2021 JAHANSHAH POURHASSAN
Quality Review Completed 11/18/2021 TARIK SAOUD
Building Plans Picked Up 11/19/2021 APPLICANT
Plan Check Approved 3/16/2022 JAHANSHAH POURHASSAN
Issued 3/30/2022 APPLICANT
CofO in Progress 5/17/2023 JOHNNY MIRANDA
Permit Finaled 6/1/2023 DANIEL ORRANTE
CofO Issued 6/1/2023 DANIEL ORRANTE
Permit Finaled 6/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 12/6/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/8/2021 DINAH GARIN
Sewer availability Cleared 12/8/2021 DINAH GARIN
Low Impact Development Cleared 1/5/2022 TA ANH
Roof/Waste drainage to street Cleared 1/14/2022 DINAH GARIN
Hydrant and Access approval Cleared 2/23/2022 JOHN CONNEALLY
Trees in Parkway Cleared 3/4/2022 ADALBERTO VERA
GPI Written Notices Cleared 3/16/2022 JAHANSHAH POURHASSAN
Grading Pre-Inspection Cleared 3/16/2022 JAHANSHAH POURHASSAN

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer M, & G Civil Engineering & Land Surveying; Lic. No.: L31604       BEVERLY HILLS, CA 90211
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/9/2022 Partial Approval OGANES TARAKHCHYAN
Sewer 5/9/2022 Approved OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/27/2022 Conditional Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 6/2/2022 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/2/2022 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 6/28/2022 No Access for Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Wood Construction 6/30/2022 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/5/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 8/9/2022 Conditional Approval JOHNNY MIRANDA
ELECTRICAL-Rough 8/9/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 8/23/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 8/25/2022 Corrections Issued JOHNNY MIRANDA
Special/Order Compliance 8/25/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 9/13/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 9/13/2022 Approved JOHNNY MIRANDA
Deputy Wood Construction 9/20/2022 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 10/5/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 10/5/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/5/2022 Partial Approval OGANES TARAKHCHYAN
Shower Pan 10/5/2022 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 10/5/2022 Approved OGANES TARAKHCHYAN
Insulation 11/15/2022 Approved JOHNNY MIRANDA
Drywall Nailing 11/28/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 11/28/2022 Approved ASHLEY THOMPSON
Gas Test 2/2/2023 Approved JOHNNY MIRANDA
Verify Rec and Parks Fee Memo 2/13/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Final 3/7/2023 Approved JOHNNY MIRANDA
HVAC-Final 3/7/2023 Approved JOHNNY MIRANDA
PLUMBING-Final 3/7/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved JOHNNY MIRANDA
Service/Power Release 3/7/2023 Not Ready for Inspection JOHNNY MIRANDA
Final 4/4/2023 Conditional Approval JOHNNY MIRANDA
Green Building Final 4/4/2023 Approved JOHNNY MIRANDA
Service/Power Release 4/4/2023 Approved JOHNNY MIRANDA
Smoke Detectors 4/4/2023 Approved JOHNNY MIRANDA
Final 5/16/2023 OK to Issue CofO JOHNNY MIRANDA
Service/Power Release 5/26/2023 Approved KENNETH NAGLE