892-892 1/2 E 41ST ST 90011

Certificate Information: 892-892 1/2 E 41ST ST 90011

Application / Permit
21010-30000-05650
Plan Check / Job No.
B21WL04763
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-story SFD & attached ADU at the front of the lot . Fully equipped w/fire sprinklers NFPA 13D. PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 ALFREDO JARA
Corrections Issued 11/8/2021 ALFREDO JARA
Quality Review Completed 11/18/2021 TARIK SAOUD
Plan Check Approved 3/2/2022 ALFREDO JARA
Issued 4/5/2022 APPLICANT
Building Plans Picked Up 4/11/2022 APPLICANT
CofO in Progress 2/15/2023 BRENDAN MORELLI
Permit Finaled 2/16/2023 DEROLD HAUFF
CofO Issued 2/16/2023 DEROLD HAUFF
Permit Finaled 2/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/30/2021 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/3/2021 JEANETTE VONG
Sewer availability Cleared 12/3/2021 JEANETTE VONG
Low Impact Development Cleared 12/14/2021 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 12/14/2021 JEANETTE VONG
Highway dedication Cleared 12/15/2021 JEANETTE VONG
Hydrant and Access approval Cleared 2/18/2022 JOHN CONNEALLY

Contact Information

Engineer Inman,, Donald J; Lic. No.: C11888 5131 FOX HILLS AVENUE      BUENA PARK, CA 90621

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/11/2022 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 4/27/2022 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 4/29/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/29/2022 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/12/2022 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 8/12/2022 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Partial Approval JOAQUIN GREENOUGH
Green Building Rough 8/18/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 8/18/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 8/19/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 8/23/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 8/23/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/2/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 9/2/2022 Corrections Issued SHAVONNE ESPINOZA
Green Building Rough 9/2/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Verify Sprinkler Sign Off 9/2/2022 Not Ready for Inspection SHAVONNE ESPINOZA
BUILDING-Rough-Frame 9/12/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 9/12/2022 Corrections Issued SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Green Building Rough 9/12/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Verify Sprinkler Sign Off 9/12/2022 Not Ready for Inspection SHAVONNE ESPINOZA
ELECTRICAL-Rough 9/15/2022 Partial Approval SHAVONNE ESPINOZA
BUILDING-Rough-Frame 9/16/2022 No Access for Inspection SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 No Access for Inspection SHAVONNE ESPINOZA
Green Building Rough 9/16/2022 No Access for Inspection SHAVONNE ESPINOZA
Verify Sprinkler Sign Off 9/16/2022 No Access for Inspection SHAVONNE ESPINOZA
Insulation 9/23/2022 Corrections Issued SHAVONNE ESPINOZA
BUILDING-Rough-Frame 9/27/2022 Conditional Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/27/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Insulation 9/27/2022 Conditional Approval ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 9/27/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 10/17/2022 Corrections Issued SHAVONNE ESPINOZA
Interior/Exterior Lathing 10/17/2022 Corrections Issued SHAVONNE ESPINOZA
BUILDING-Rough-Frame 2/2/2023 Approved BRENDAN MORELLI
Green Building Final 2/2/2023 Approved BRENDAN MORELLI
Green Building Rough 2/2/2023 Approved BRENDAN MORELLI
HVAC-Final 2/2/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 2/2/2023 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 2/2/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 2/6/2023 Approved BRENDAN MORELLI
Final 2/6/2023 Conditional Approval BRENDAN MORELLI
HVAC-Final 2/6/2023 Approved BRENDAN MORELLI
PLUMBING-Final 2/6/2023 Approved BRENDAN MORELLI
Service/Power Release 2/6/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 2/10/2023 Approved BRENDAN MORELLI
Final 2/10/2023 OK to Issue CofO BRENDAN MORELLI