894-894 1/2 E 41ST ST 90011
Certificate Information: 894-894 1/2 E 41ST ST 90011
- Application / Permit
- 21010-30000-05648
- Plan Check / Job No.
- B21WL04763
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 3-story Duplex w/attached garage at the rear of the lot. Fully equipped w/fire sprinklers NFPA 13D
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 2/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | ALFREDO JARA |
| Corrections Issued | 11/8/2021 | ALFREDO JARA |
| Quality Review Completed | 11/18/2021 | TARIK SAOUD |
| Plan Check Approved | 3/2/2022 | ALFREDO JARA |
| Issued | 4/5/2022 | APPLICANT |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| CofO in Progress | 2/15/2023 | BRENDAN MORELLI |
| CofO Issued | 2/22/2023 | DEROLD HAUFF |
| Permit Finaled | 2/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 12/3/2021 | JEANETTE VONG |
| Low Impact Development | Cleared | 12/14/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | JEANETTE VONG |
| Highway dedication | Cleared | 12/15/2021 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 2/18/2022 | JOHN CONNEALLY |
Contact Information
| Engineer | Inman,, Donald J; Lic. No.: C11888 | 5131 FOX HILLS AVENUE BUENA PARK, CA 90621 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 4/27/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 4/29/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/29/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/12/2022 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 8/12/2022 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 8/17/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 8/17/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/23/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/23/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 9/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Green Building Rough | 9/2/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Verify Sprinkler Sign Off | 9/2/2022 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 9/7/2022 | Approved | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 9/12/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Green Building Rough | 9/12/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 9/15/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Green Building Rough | 9/15/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Insulation | 9/23/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 9/27/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 10/15/2022 | Approved | RICHARD ROBLES |
| Interior/Exterior Lathing | 10/15/2022 | Partial Approval | RICHARD ROBLES |
| Drywall Nailing | 10/17/2022 | Approved | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 10/17/2022 | Partial Approval | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 2/2/2023 | Approved | BRENDAN MORELLI |
| Green Building Final | 2/2/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 2/2/2023 | Approved | BRENDAN MORELLI |
| HVAC-Final | 2/2/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 2/2/2023 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 2/2/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 2/6/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 2/6/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Final | 2/6/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 2/6/2023 | Approved | BRENDAN MORELLI |
| Service/Power Release | 2/6/2023 | Approved | BRENDAN MORELLI |
| Final | 2/10/2023 | OK to Issue CofO | BRENDAN MORELLI |