2039 S BARRY AVE 90025

Certificate Information: 2039 S BARRY AVE 90025

Application / Permit
21010-30000-05603
Plan Check / Job No.
B21WL04749
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-story house with 2-car garage & roof trusses
Permit Issued
Issued on 7/8/2022
Issuing Office
Current Status
CofO Issued on 10/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 11/23/2021 HOOMAN HAJIZADEH
Corrections Issued 12/2/2021 HOOMAN HAJIZADEH
Quality Review Completed 12/13/2021 TARIK SAOUD
Building Plans Picked Up 12/14/2021 APPLICANT
Plan Check Approved 6/17/2022 HOOMAN HAJIZADEH
Issued 7/8/2022 APPLICANT
CofO in Progress 9/23/2023 CHRISTOPHER WILSON
CofO in Progress 9/23/2023 CHRISTOPHER WILSON
Permit Finaled 10/7/2023 DANIEL ORRANTE
CofO Issued 10/7/2023 DANIEL ORRANTE
Permit Finaled 10/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/21/2021 DINAH GARIN
Miscellaneous Cleared 12/21/2021 DALIA MOKAYED
Permit Cleared 12/21/2021 DINAH GARIN
ZA Case Cleared 12/21/2021 DALIA MOKAYED
Eng Process Fee Ord 176,300 Cleared 12/22/2021 DINAH GARIN
Sewer availability Cleared 12/22/2021 DINAH GARIN
Specific Plan Cleared 12/22/2021 EDUARDO HERMOSO
Trees in Parkway Cleared 2/16/2022 ADALBERTO VERA
Low Impact Development Cleared 3/7/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 3/21/2022 DINAH GARIN
Hydrant and Access approval Cleared 5/6/2022 GILBERT URREA

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/30/2022 Partial Approval ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 12/22/2022 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 12/23/2022 Approved ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 12/23/2022 Approved ASHLEY THOMPSON
Footing/Foundation/Slab 12/23/2022 Approved ASHLEY THOMPSON
Sewer 1/17/2023 No Access for Inspection CLAYTON GRAHAM
Sewer 1/23/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Partial Approval CLAYTON GRAHAM
Special/Order Compliance 3/20/2023 Partial Inspection JESUS PINEDA
Deputy Wood Construction 4/5/2023 Conditional Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Corrections Issued CLAYTON GRAHAM
Gas Test 4/24/2023 Approved JESUS PINEDA
PLUMBING-Rough 4/24/2023 Corrections Issued JESUS PINEDA
PLUMBING-Rough 4/27/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval HERBERT GIRON
HVAC-Rough 5/16/2023 Approved JEREMY TODD
Shower Pan 5/16/2023 Not Ready for Inspection JEREMY TODD
ELECTRICAL-Rough 5/22/2023 Corrections Issued JESUS PINEDA
Shower Pan 5/22/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 5/24/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/30/2023 Corrections Issued JESUS PINEDA
Green Building Rough 5/30/2023 Not Ready for Inspection JESUS PINEDA
Interior/Exterior Lathing 5/30/2023 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 5/30/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 6/1/2023 Partial Approval MICHAEL PELHAM
Green Building Rough 6/1/2023 Not Ready for Inspection MICHAEL PELHAM
Interior/Exterior Lathing 6/1/2023 Not Ready for Inspection MICHAEL PELHAM
BUILDING-Rough-Frame 6/8/2023 Approved JESUS PINEDA
Green Building Rough 6/8/2023 Approved JESUS PINEDA
Insulation 6/8/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 6/8/2023 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 6/14/2023 Approved JESUS PINEDA
Drywall Nailing 6/20/2023 Approved JESUS PINEDA
ELECTRICAL-Final 9/8/2023 Approved MEL KHACHATOURIAN
Gas Test 9/8/2023 Approved MEL KHACHATOURIAN
HVAC-Final 9/8/2023 Approved MEL KHACHATOURIAN
Gas Test 9/11/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 9/11/2023 Approved ARAM AVEDISIAN
Final 9/20/2023 OK to Issue CofO CHRISTOPHER WILSON
Green Building Final 9/20/2023 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/20/2023 SGSOV Approved CHRISTOPHER WILSON
Service/Power Release 9/20/2023 Approved CHRISTOPHER WILSON
Smoke Detectors 9/20/2023 Approved CHRISTOPHER WILSON