119 S LA JOLLA AVE Main House 90048
Certificate Information: 119 S LA JOLLA AVE Main House 90048
- Application / Permit
- 21010-30000-05589
- Plan Check / Job No.
- B21WL04717
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD (2,493 sf) w./ att. 2-car garage (351 sf) and roof deck
- Permit Issued
- Issued on 4/27/2022
- Issuing Office
- Current Status
- CofO Issued on 9/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | REZA HAGHIGHAT |
| Corrections Issued | 11/6/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 11/17/2021 | TARIK SAOUD |
| Building Plans Picked Up | 11/19/2021 | APPLICANT |
| Applicant returned to address corrections | 3/22/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 4/13/2022 | REZA HAGHIGHAT |
| Issued | 4/27/2022 | APPLICANT |
| CofO in Progress | 9/1/2023 | DAVID FEILER |
| Permit Finaled | 9/8/2023 | DANIEL ORRANTE |
| CofO Issued | 9/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2021 | STEVE MELGAR |
| Permit | Cleared | 12/3/2021 | STEVE MELGAR |
| ZA Case | Cleared | 12/20/2021 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 1/3/2022 | STEVE MELGAR |
| Trees in Parkway | Cleared | 1/6/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 1/21/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/24/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 2/28/2022 | LAURINDA MEADE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2022 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 5/2/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 5/2/2022 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 6/10/2022 | Conditional Approval | EVAN COOPER |
| METHANE-Barrier | 6/10/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 6/10/2022 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 6/10/2022 | Corrections Issued | EVAN COOPER |
| METHANE-Subgrade | 6/14/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 6/14/2022 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 6/17/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 6/17/2022 | Partial Approval | EVAN COOPER |
| METHANE-Subgrade | 6/17/2022 | Approved | EVAN COOPER |
| Deputy Methane Barrier | 7/6/2022 | Conditional Approval | EVAN COOPER |
| Deputy Methane Barrier | 7/7/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/11/2022 | Approved | EVAN COOPER |
| METHANE-Barrier | 7/11/2022 | Approved | EVAN COOPER |
| METHANE-Final | 7/11/2022 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 7/11/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Partial Approval | EVAN COOPER |
| Green Building Rough | 8/5/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 8/5/2022 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 8/5/2022 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 10/17/2022 | Conditional Approval | ANDREW NAVE |
| Underground Mechanical | 10/17/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 10/20/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 11/1/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 11/15/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 11/15/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 11/17/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 11/17/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 12/6/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 12/6/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Rough | 12/6/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/6/2022 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Rough | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/13/2022 | Partial Approval | JEREMY TODD |
| Green Building Rough | 12/13/2022 | Approved | JEREMY TODD |
| Insulation | 12/13/2022 | Corrections Issued | JEREMY TODD |
| Special/Order Compliance | 12/13/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 12/16/2022 | Approved | JEREMY TODD |
| Drywall Nailing | 12/22/2022 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 12/22/2022 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 6/20/2023 | Corrections Issued | JEREMY TODD |
| HVAC-Final | 6/20/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 6/20/2023 | Not Ready for Inspection | JEREMY TODD |
| Service/Power Release | 6/20/2023 | Not Ready for Inspection | JEREMY TODD |
| ELECTRICAL-Final | 6/29/2023 | Approved | JEREMY TODD |
| HVAC-Final | 6/29/2023 | Approved | JEREMY TODD |
| Service/Power Release | 6/29/2023 | Not Ready for Inspection | JEREMY TODD |
| PLUMBING-Final | 6/30/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 7/11/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/14/2023 | Approved | MEL KHACHATOURIAN |
| Final | 8/14/2023 | OK to Issue CofO | MEL KHACHATOURIAN |
| Green Building Final | 8/14/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Approved | MEL KHACHATOURIAN |
| Service/Power Release | 8/14/2023 | Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 8/14/2023 | Approved | MEL KHACHATOURIAN |