831 N ORANGE GROVE AVE 90046

Certificate Information: 831 N ORANGE GROVE AVE 90046

Application / Permit
21010-30000-05540
Plan Check / Job No.
B21WL04698
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(n) 2 family dwelling. both w/ (n) car garage & roof trusses
Permit Issued
Issued on 6/15/2022
Issuing Office
Current Status
CofO Issued on 4/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 FELIPE HERNANDEZ
Corrections Issued 11/9/2021 FELIPE HERNANDEZ
Quality Review Completed 11/18/2021 TARIK SAOUD
Applicant returned to address corrections 5/31/2022 FELIPE HERNANDEZ
Plan Check Approved 6/9/2022 FELIPE HERNANDEZ
Issued 6/15/2022 APPLICANT
Building Plans Picked Up 6/16/2022 APPLICANT
CofO in Progress 4/26/2023 MICHAEL LEWIS
No Progress 4/27/2023 SCOTT FINNILA
CofO in Progress 4/27/2023 SCOTT FINNILA
CofO in Progress 4/27/2023 SCOTT FINNILA
CofO in Progress 4/27/2023 SCOTT FINNILA
Permit Finaled 4/30/2023 DEROLD HAUFF
Permit Finaled 4/30/2023 DEROLD HAUFF
CofO Issued 4/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 12/21/2021 ADALBERTO VERA
Low Impact Development Cleared 1/11/2022 MARCO SANCHEZ
Address approval Cleared 1/13/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/13/2022 STEVE MELGAR
Permit Cleared 1/13/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 1/13/2022 STEVE MELGAR
Sewer availability Cleared 1/13/2022 STEVE MELGAR
Hydrant and Access approval Cleared 2/11/2022 KURT CORRAL

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/11/2022 Approved ALIZAH MAYAGOITIA
Underground Mechanical 7/11/2022 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 7/22/2022 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 7/22/2022 Conditional Approval JOSEPH MCGARRY
Sewer 8/16/2022 Corrections Issued MICHAEL LEWIS
Sewer 8/17/2022 Approved MICHAEL LEWIS
Deputy Wood Construction 8/30/2022 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Approved MICHAEL LEWIS
Deputy Wood Construction 10/4/2022 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved MICHAEL LEWIS
Deputy Wood Construction 11/1/2022 Conditional Approval MICHAEL LEWIS
Deputy Wood Construction 11/3/2022 Conditional Approval MICHAEL LEWIS
BUILDING-Rough-Frame 11/9/2022 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 11/9/2022 Approved MICHAEL LEWIS
Green Building Rough 11/9/2022 Approved MICHAEL LEWIS
HVAC-Rough 11/9/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 11/9/2022 Approved MICHAEL LEWIS
Shower Pan 11/9/2022 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 11/9/2022 Not Ready for Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 12/14/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 12/14/2022 Partial Approval MICHAEL LEWIS
Verify Sprinkler Sign Off 12/14/2022 Approved MICHAEL LEWIS
Insulation 12/20/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 12/20/2022 Approved MICHAEL LEWIS
Drywall Nailing 1/3/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/20/2023 Approved MICHAEL LEWIS
Underground Mechanical 1/27/2023 Not Ready for Inspection MICHAEL LEWIS
Underground Mechanical 2/21/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 2/27/2023 No Access for Inspection MICHAEL LEWIS
PLUMBING-Final 2/27/2023 No Access for Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Not Ready MICHAEL LEWIS
Gas Test 3/3/2023 Approved MICHAEL LEWIS
PLUMBING-Final 3/3/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 3/14/2023 Approved MICHAEL LEWIS
HVAC-Final 3/14/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 3/14/2023 Approved MICHAEL LEWIS
Final 3/21/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 3/21/2023 Approved MICHAEL LEWIS
Green Building Final 3/21/2023 Approved MICHAEL LEWIS
Smoke Detectors 3/21/2023 Approved MICHAEL LEWIS
Final 4/26/2023 OK to Issue CofO MICHAEL LEWIS