1512 E 22ND ST 90011
Certificate Information: 1512 E 22ND ST 90011
- Application / Permit
- 21010-30000-05532
- Plan Check / Job No.
- B21WL04682
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-story ADU above 2-car garage per Ordinance, LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/3/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | HOOMAN HAJIZADEH |
| Corrections Issued | 11/24/2021 | HOOMAN HAJIZADEH |
| Quality Review Completed | 12/6/2021 | TARIK SAOUD |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| Applicant returned to address corrections | 4/8/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 4/13/2022 | HOOMAN HAJIZADEH |
| Plan Check Approved | 6/8/2022 | HOOMAN HAJIZADEH |
| Issued | 3/3/2023 | APPLICANT |
| CofO in Progress | 2/5/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
| CofO Issued | 2/11/2025 | DEROLD HAUFF |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/8/2021 | KHOUNG LE |
| Historic Resource Verification | Cleared | 12/9/2021 | MICAELA TORRES-GIL |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | KHOUNG LE |
| Low Impact Development | Cleared | 1/3/2022 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 1/3/2022 | KHOUNG LE |
| Sewer availability | Cleared | 1/3/2022 | KHOUNG LE |
| Redevelopment Project Area | Cleared | 1/6/2022 | GRACIELA ACOSTA |
| Hydrant and Access approval | Cleared | 3/26/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Funes Construction Inc; Lic. No.: 1028108-B | 14154 ERWIN ST APT 6 VAN NUYS, CA 91401 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/25/2023 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 4/25/2023 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 5/5/2023 | Approved | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 5/8/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 6/28/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 10/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 10/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/20/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/20/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/20/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/20/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/20/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/27/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/2/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/24/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Final | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 9/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 9/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 9/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 9/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 9/25/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 9/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 9/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/4/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |