1605 W 207TH ST 90501

Certificate Information: 1605 W 207TH ST 90501

Application / Permit
21010-30000-05529
Plan Check / Job No.
B21WL04680
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story ADU per LAMC 12.22 A.33(c) AND (d) (820 sf)
Permit Issued
Issued on 6/2/2022
Issuing Office
Current Status
CofO Issued on 8/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 REZA HAGHIGHAT
Corrections Issued 11/23/2021 REZA HAGHIGHAT
Quality Review Completed 12/2/2021 TARIK SAOUD
Plan Check Approved 5/9/2022 REZA HAGHIGHAT
Issued 6/2/2022 APPLICANT
Building Plans Picked Up 6/3/2022 APPLICANT
CofO in Progress 8/1/2023 EUGENE CASSIDY
Permit Finaled 8/1/2023 ANSON MAGLASANG
CofO Issued 8/1/2023 ANSON MAGLASANG
Permit Finaled 8/1/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/22/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 12/2/2021 ERIK BEASLEY
Sewer availability Cleared 12/3/2021 ERIK BEASLEY
Frnt yard landscape/Water mgmt Cleared 12/21/2021 LAUREN PADICK
Hydrant and Access approval Cleared 3/1/2022 JOHN CONNEALLY
Low Impact Development Cleared 5/2/2022 TA ANH
Roof/Waste drainage to street Cleared 5/2/2022 ERIK BEASLEY

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/22/2022 Not Ready for Inspection EUGENE CASSIDY
Sewer 6/22/2022 Approved EUGENE CASSIDY
Underground Mechanical 6/22/2022 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 6/29/2022 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/11/2022 Approved EUGENE CASSIDY
Footing/Foundation/Slab 7/11/2022 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 7/12/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/16/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Partial Approval JOHN KLARIN
Deputy Wood Construction 12/15/2022 No Result Entered BOB GOBUTY
ELECTRICAL-Rough 1/31/2023 Approved EUGENE CASSIDY
HVAC-Rough 1/31/2023 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 1/31/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 2/16/2023 Conditional Approval EUGENE CASSIDY
Gas Test 2/16/2023 Approved EUGENE CASSIDY
HVAC-Rough 2/16/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 2/16/2023 Approved EUGENE CASSIDY
Insulation 2/27/2023 Approved EUGENE CASSIDY
Drywall Nailing 3/6/2023 Approved EUGENE CASSIDY
Insulation 3/6/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/6/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/5/2023 Partial Approval EUGENE CASSIDY
HVAC-Final 7/5/2023 Approved EUGENE CASSIDY
PLUMBING-Final 7/5/2023 Approved EUGENE CASSIDY
Service/Power Release 7/5/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 7/25/2023 Approved EUGENE CASSIDY
Final 7/25/2023 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 7/25/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/25/2023 SGSOV Approved EUGENE CASSIDY
Service/Power Release 7/25/2023 Approved EUGENE CASSIDY
Smoke Detectors 7/25/2023 Approved EUGENE CASSIDY
Final 7/31/2023 OK to Issue CofO EUGENE CASSIDY