11435 W BELLAGIO ROAD 90049
Certificate Information: 11435 W BELLAGIO ROAD 90049
- Application / Permit
- 21010-30000-05516
- Plan Check / Job No.
- B21WL04655
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR AND 2ND FLOOR ADDITION TO AN EXISTING SDF WITH ATTACHED GARAGE
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | KAVIAN REFAHI |
| Plans on Hold | 11/1/2021 | KAVIAN REFAHI |
| Hold Released | 11/5/2021 | KAVIAN REFAHI |
| Corrections Issued | 11/8/2021 | KAVIAN REFAHI |
| Quality Review Completed | 11/16/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 5/3/2022 | KAVIAN REFAHI |
| Plan Check Approved | 5/11/2022 | KAVIAN REFAHI |
| Issued | 6/3/2022 | APPLICANT |
| Building Plans Picked Up | 6/3/2022 | APPLICANT |
| CofO in Progress | 11/16/2023 | STEPHANIE SWANSON |
| Permit Finaled | 11/18/2023 | DANIEL ORRANTE |
| CofO Issued | 11/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 11/5/2021 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 11/5/2021 | KAVIAN REFAHI |
| Low Impact Development | Cleared | 4/11/2022 | ANTHONY VARGAS |
| BHO/Hillside ordinance | Cleared | 5/4/2022 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/4/2022 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/4/2022 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/4/2022 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/4/2022 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 5/4/2022 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 6/2/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Gardinier Robert Edward Jr; Lic. No.: 630409-B | 1156 NORIA ST LAGUNA BEACH, CA 92651 |
| Engineer | Lee,, Jack C; Lic. No.: GE2153 | 576 E LAMBERT RD BREA, CA 92821 |
| Engineer | Vasquez,, Mario Alberto; Lic. No.: C89006 | 43023 40TH ST WEST LANCASTER, CA 93536 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/7/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 6/16/2022 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/21/2022 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 6/24/2022 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 7/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 7/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/29/2022 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/2/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Wood Construction | 8/2/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/2/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/2/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 8/2/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/2/2022 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 8/26/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/26/2022 | No Access for Inspection | CARLOS MATAMOROS |
| Shower Pan | 8/26/2022 | No Access for Inspection | CARLOS MATAMOROS |
| Drywall Nailing | 8/30/2022 | Partial Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/30/2022 | Partial Approval | CARLOS MATAMOROS |
| Shower Pan | 8/30/2022 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 8/31/2022 | Conditional Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 9/1/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 9/1/2022 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/1/2022 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 9/14/2022 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/14/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 10/31/2022 | Approved | CHRISTOPHER WILSON |
| Gas Test | 10/31/2022 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Service/Power Release | 10/31/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 11/16/2022 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 12/1/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 12/1/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | STEPHANIE SWANSON |
| Final | 11/15/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/15/2023 | Approved | STEPHANIE SWANSON |
| Green Building Final | 11/15/2023 | Approved | STEPHANIE SWANSON |
| Smoke Detectors | 11/15/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 11/16/2023 | OK to Issue CofO | STEPHANIE SWANSON |
| Smoke Detectors | 11/16/2023 | Approved | STEPHANIE SWANSON |