130 1/2 N MOTT ST 90033
Certificate Information: 130 1/2 N MOTT ST 90033
- Application / Permit
- 21010-30000-05456
- Plan Check / Job No.
- B21WL04581
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ADU AND STORAGE
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | TARIK SAOUD |
| Corrections Issued | 11/9/2021 | TARIK SAOUD |
| Quality Review Completed | 11/9/2021 | CHIHARU SUZUKI |
| Building Plans Picked Up | 11/16/2021 | APPLICANT |
| Applicant returned to address corrections | 2/18/2022 | TARIK SAOUD |
| Plan Check Approved | 2/18/2022 | TARIK SAOUD |
| Issued | 4/1/2022 | APPLICANT |
| CofO in Progress | 11/29/2023 | FREDDIE RIVERA |
| Permit Finaled | 12/15/2023 | DEROLD HAUFF |
| CofO Issued | 12/15/2023 | DEROLD HAUFF |
| Permit Finaled | 12/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/22/2021 | PATRICK MISCHLICH |
| Clean Up Green Up | Cleared | 12/23/2021 | RICHARD REASER |
| Low Impact Development | Cleared | 1/14/2022 | TA ANH |
| Address approval | Cleared | 1/20/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 1/20/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | CINDY QI |
| Sewer availability | Cleared | 1/26/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 2/3/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | R E T Construction Corp; Lic. No.: 1019820-B | 8035 LINWALT ST ROSEMEAD, CA 91770 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/26/2022 | Corrections Issued | FREDDIE RIVERA |
| Grounding or Bonding | 4/26/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/3/2022 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/3/2022 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Barrier | 5/3/2022 | Conditional Approval | FREDDIE RIVERA |
| METHANE-Subgrade | 5/3/2022 | Conditional Approval | FREDDIE RIVERA |
| Sewer | 5/3/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/15/2022 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 6/15/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 6/15/2022 | Approved | FREDDIE RIVERA |
| Structural Steel Frame | 6/15/2022 | Conditional Approval | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 6/17/2022 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/29/2022 | Order to Comply Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/12/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 10/12/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 10/12/2022 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 10/12/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 10/12/2022 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 10/12/2022 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/20/2022 | Conditional Approval | FREDDIE RIVERA |
| Green Building Rough | 10/20/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 10/20/2022 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 10/20/2022 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 10/20/2022 | Approved | FREDDIE RIVERA |
| Insulation | 11/28/2022 | Conditional Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 11/28/2022 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 1/3/2023 | Approved | FREDDIE RIVERA |
| Gas Test | 3/17/2023 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 3/17/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/17/2023 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 4/17/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/22/2023 | Approved | FREDDIE RIVERA |
| Final | 5/22/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 5/22/2023 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Final | 5/22/2023 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 5/22/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/22/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 5/22/2023 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 5/22/2023 | Approved | FREDDIE RIVERA |
| Final | 11/21/2023 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 11/21/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | FREDDIE RIVERA |
| Final | 11/28/2023 | OK to Issue CofO | FREDDIE RIVERA |