2103-2103 1/2 S BURNSIDE AVE 90016
Certificate Information: 2103-2103 1/2 S BURNSIDE AVE 90016
- Application / Permit
- 21010-30000-05391
- Plan Check / Job No.
- B21WL04519
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3 story Duplex in rear *** 2 of 2 ***
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- CofO Issued on 5/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | HOOMAN HAJIZADEH |
| Corrections Issued | 11/10/2021 | HOOMAN HAJIZADEH |
| Quality Review Completed | 11/22/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 3/2/2022 | HOOMAN HAJIZADEH |
| Plan Check Approved | 3/4/2022 | HOOMAN HAJIZADEH |
| Issued | 3/24/2022 | APPLICANT |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| CofO in Progress | 4/28/2023 | JOSE AVILA |
| Permit Finaled | 5/4/2023 | DEROLD HAUFF |
| CofO Issued | 5/4/2023 | DEROLD HAUFF |
| Permit Finaled | 5/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 12/3/2021 | JEANETTE VONG |
| Low Impact Development | Cleared | 12/14/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 2/17/2022 | JOHN CONNEALLY |
Contact Information
| Architect | Hamid, Dehghan; Lic. No.: C35150 | 2355 WESTWOOD BLVD # 900 LOS ANGELES, CA 90064 |
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/1/2022 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/13/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 4/13/2022 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/14/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 10/12/2022 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 10/13/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 10/27/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 10/27/2022 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 10/27/2022 | Corrections Issued | JOSE AVILA |
| Verify Sprinkler Sign Off | 10/27/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/16/2022 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 11/16/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 11/16/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/1/2022 | Not Ready for Inspection | JOSE AVILA |
| Insulation | 12/1/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/1/2022 | Not Ready for Inspection | JOSE AVILA |
| Shower Pan | 12/1/2022 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 12/5/2022 | Approved | JOSE AVILA |
| Shower Pan | 12/5/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 4/14/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 4/14/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 4/17/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 4/17/2023 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 4/17/2023 | Approved | JOSE AVILA |
| Green Building Rough | 4/17/2023 | Approved | JOSE AVILA |
| Final | 4/21/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 4/21/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 4/21/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 4/21/2023 | Approved | JOSE AVILA |
| Final | 4/28/2023 | OK to Issue CofO | JOSE AVILA |