2103-2103 1/2 S BURNSIDE AVE 90016

Certificate Information: 2103-2103 1/2 S BURNSIDE AVE 90016

Application / Permit
21010-30000-05391
Plan Check / Job No.
B21WL04519
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3 story Duplex in rear *** 2 of 2 ***
Permit Issued
Issued on 3/24/2022
Issuing Office
Current Status
CofO Issued on 5/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 HOOMAN HAJIZADEH
Corrections Issued 11/10/2021 HOOMAN HAJIZADEH
Quality Review Completed 11/22/2021 TARIK SAOUD
Applicant returned to address corrections 3/2/2022 HOOMAN HAJIZADEH
Plan Check Approved 3/4/2022 HOOMAN HAJIZADEH
Issued 3/24/2022 APPLICANT
Building Plans Picked Up 3/25/2022 APPLICANT
CofO in Progress 4/28/2023 JOSE AVILA
Permit Finaled 5/4/2023 DEROLD HAUFF
CofO Issued 5/4/2023 DEROLD HAUFF
Permit Finaled 5/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/30/2021 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/3/2021 JEANETTE VONG
Sewer availability Cleared 12/3/2021 JEANETTE VONG
Low Impact Development Cleared 12/14/2021 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 12/14/2021 JEANETTE VONG
Hydrant and Access approval Cleared 2/17/2022 JOHN CONNEALLY

Contact Information

Architect Hamid, Dehghan; Lic. No.: C35150 2355 WESTWOOD BLVD   # 900    LOS ANGELES, CA 90064
Contractor Daniel Pascuale; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/1/2022 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/13/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/13/2022 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/14/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 10/12/2022 Corrections Issued JOSE AVILA
Deputy Wood Construction 10/13/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 10/27/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Corrections Issued JOSE AVILA
HVAC-Rough 10/27/2022 Partial Approval JOSE AVILA
PLUMBING-Rough 10/27/2022 Corrections Issued JOSE AVILA
Verify Sprinkler Sign Off 10/27/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 11/16/2022 Partial Approval JOSE AVILA
Interior/Exterior Lathing 11/16/2022 Approved JOSE AVILA
PLUMBING-Rough 11/16/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 12/1/2022 Not Ready for Inspection JOSE AVILA
Insulation 12/1/2022 Approved JOSE AVILA
Interior/Exterior Lathing 12/1/2022 Not Ready for Inspection JOSE AVILA
Shower Pan 12/1/2022 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 12/5/2022 Approved JOSE AVILA
Shower Pan 12/5/2022 Approved JOSE AVILA
ELECTRICAL-Final 4/14/2023 Corrections Issued JOSE AVILA
PLUMBING-Final 4/14/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 4/17/2023 Approved JOSE AVILA
Drywall Nailing 4/17/2023 Approved JOSE AVILA
Footing/Foundation/Slab 4/17/2023 Approved JOSE AVILA
Green Building Rough 4/17/2023 Approved JOSE AVILA
Final 4/21/2023 Corrections Issued JOSE AVILA
Green Building Final 4/21/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved JOSE AVILA
Service/Power Release 4/21/2023 Approved JOSE AVILA
Smoke Detectors 4/21/2023 Approved JOSE AVILA
Final 4/28/2023 OK to Issue CofO JOSE AVILA