11449 W CUMPSTON ST 1-2 91601

Certificate Information: 11449 W CUMPSTON ST 1-2 91601

Application / Permit
21010-30000-05356
Plan Check / Job No.
B21WL04506
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-story Duplex w./ att. garage at rear of the lot. Fully equipped w/fire sprinkler system NFPA 13R
Permit Issued
Issued on 4/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 ALFREDO JARA
Corrections Issued 10/26/2021 ALFREDO JARA
Quality Review Completed 11/4/2021 TARIK SAOUD
Plan Check Approved 4/27/2022 ALFREDO JARA
Building Plans Picked Up 4/28/2022 APPLICANT
Issued 4/29/2022 APPLICANT
CofO in Progress 1/16/2025 CHRISTOPHER ROJAS
CofO in Progress 1/17/2025 CHRISTOPHER ROJAS
Permit Finaled 2/4/2025 RUBEN SALAS
CofO Issued 2/4/2025 RUBEN SALAS
Permit Finaled 2/4/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/30/2021 CARLOS AGUILERA
Highway dedication Cleared 10/30/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/1/2021 CARLOS AGUILERA
Sewer availability Cleared 11/1/2021 CARLOS AGUILERA
Low Impact Development Cleared 3/1/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 3/1/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/31/2022 RUEL COLE

Contact Information

Contractor On Point Builders Inc; Lic. No.: 928105-B 2371 GRAND AVE #90902      LONG BEACH, CA 90809
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2022 Partial Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/2/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 6/2/2022 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 7/11/2022 Approved DAVID MATSON
Footing/Foundation/Slab 7/11/2022 Approved DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Partial Approval JACK KARGODORIAN
HVAC-Rough 2/14/2023 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 2/14/2023 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 3/14/2023 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Partial Approval JACK KARGODORIAN
HVAC-Rough 3/14/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 3/14/2023 Approved JACK KARGODORIAN
Pre-Inspection 9/28/2023 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 11/2/2023 Corrections Issued JOHN COLEMAN
Underground Mechanical 11/2/2023 Conditional Approval JOHN COLEMAN
Footing/Foundation/Slab 12/4/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 12/15/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/22/2024 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Partial Approval KIRK SANDERS
HVAC-Rough 6/5/2024 Conditional Approval CHRISTOPHER ROJAS
PLUMBING-Rough 6/5/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/12/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/12/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/12/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/28/2024 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 6/28/2024 Approved VINCENT HANLEY
Green Building Rough 6/28/2024 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 6/28/2024 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 7/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 7/12/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 7/12/2024 Approved CHRISTOPHER ROJAS
Insulation 7/24/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 8/5/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/5/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/23/2024 Corrections Issued CHRISTOPHER ROJAS
Gas Test 12/23/2024 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Final 12/23/2024 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 12/26/2024 Partial Inspection CHRISTOPHER ROJAS
Final 12/26/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 12/26/2024 Partial Inspection CHRISTOPHER ROJAS
Smoke Detectors 12/26/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/6/2025 Approved CHRISTOPHER ROJAS
Final 1/6/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 1/6/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/6/2025 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 1/6/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 1/16/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Final 1/16/2025 Approved CHRISTOPHER ROJAS
Service/Power Release 1/16/2025 Approved CHRISTOPHER ROJAS