1706 N MANDEVILLE LANE 90049

Certificate Information: 1706 N MANDEVILLE LANE 90049

Application / Permit
21010-30000-05328
Plan Check / Job No.
B21WL04480
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story SFD with attached garage. ***See Comments***
Permit Issued
Issued on 3/19/2022
Issuing Office
Current Status
CofO Issued on 3/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 JAHANSHAH POURHASSAN
Corrections Issued 10/28/2021 JAHANSHAH POURHASSAN
Quality Review Completed 11/17/2021 TARIK SAOUD
Applicant returned to address corrections 12/21/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 1/27/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 1/31/2022 JAHANSHAH POURHASSAN
Applicant returned to address corrections 3/4/2022 JAHANSHAH POURHASSAN
Plan Check Approved 3/15/2022 JAHANSHAH POURHASSAN
Issued 3/19/2022 APPLICANT
Building Plans Picked Up 4/1/2022 APPLICANT
CofO in Progress 3/5/2024 KEVIN SARGSYAN
Permit Finaled 3/9/2024 DANIEL ORRANTE
CofO Issued 3/9/2024 DANIEL ORRANTE
Permit Finaled 3/9/2024 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/27/2021 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 11/27/2021 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 11/27/2021 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 11/27/2021 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 11/27/2021 MAHELET GEBEYHU
Sewer availability Cleared 11/27/2021 MAHELET GEBEYHU
Watercourse Cleared 11/27/2021 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 12/1/2021 MAHELET GEBEYHU
Low Impact Development Cleared 1/27/2022 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 2/2/2022 MAHELET GEBEYHU
Trees in Parkway Cleared 2/2/2022 JAHANSHAH POURHASSAN
Permit Cleared 2/14/2022 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 2/18/2022 LAURINDA MEADE
GPI Written Notices Cleared 3/4/2022 JAHANSHAH POURHASSAN
Grading Pre-Inspection Cleared 3/4/2022 JAHANSHAH POURHASSAN

Contact Information

Architect Radziner,, Ronald Mark; Lic. No.: C22228 MARMOL RADZINER & ASSOCIATES   12210 NEBRASKA AVE    LOS ANGELES, CA 90025
Contractor Marmol Radziner An Architectural Corporation; Lic. No.: 734381-B 12210 NEBRASKA AVENUE      LOS ANGELES, CA 90025
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Hennon,, Robert David; Lic. No.: L5573 601 E GLENOAKS BLVD 208      GLENDALE, CA 91207
Engineer Wavering,, Derek Evan; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/25/2022 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/6/2022 Partial Inspection JUAN VALENZUELA
Underground Mechanical 5/20/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/23/2022 Partial Approval JUAN VALENZUELA
Underground Mechanical 5/23/2022 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/14/2022 Approved JUAN VALENZUELA
Footing/Foundation/Slab 6/14/2022 Approved JUAN VALENZUELA
Underground Mechanical 6/14/2022 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 No Access for Inspection KENNETH NAGLE
Wood Frame 8/15/2022 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Partial Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 11/18/2022 Conditional Approval JUAN VALENZUELA
HVAC-Rough 11/18/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Corrections Issued KENNETH NAGLE
PLUMBING-Rough 12/7/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 12/22/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 1/18/2023 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 1/19/2023 Partial Approval KEVIN SARGSYAN
Sewer 2/1/2023 Approved KEVIN SARGSYAN
Underground Mechanical 2/3/2023 Partial Approval KEVIN SARGSYAN
Underground Mechanical 2/17/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 2/27/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval KEVIN SARGSYAN
Verify Sprinkler Sign Off 3/14/2023 Approved KEVIN SARGSYAN
FLOOD-Proofing Certificate 3/16/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 No Access for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 3/21/2023 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 3/28/2023 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 4/3/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Partial Approval KEVIN SARGSYAN
Green Building Rough 4/3/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 4/4/2023 Approved KEVIN SARGSYAN
Deputy Wood Construction 4/4/2023 Conditional Approval JESUS PINEDA
Insulation 4/6/2023 Approved KEVIN SARGSYAN
Wood Frame 4/6/2023 Approved KEVIN SARGSYAN
Drywall Nailing 4/17/2023 Approved JESUS PINEDA
Shower Pan 4/17/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 5/1/2023 Approved KEVIN SARGSYAN
PLUMBING-Rough 9/20/2023 Approved KEVIN SARGSYAN
Gas Test 9/25/2023 Partial Approval KEVIN SARGSYAN
Underground Mechanical 9/25/2023 Approved KEVIN SARGSYAN
Gas Test 11/20/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 11/28/2023 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 12/29/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 12/29/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 1/5/2024 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 1/5/2024 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 1/9/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 1/10/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 1/12/2024 Approved KEVIN SARGSYAN
Green Building Final 2/23/2024 Approved KEVIN SARGSYAN
Final 3/4/2024 OK to Issue CofO KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 3/4/2024 Approved KEVIN SARGSYAN
Smoke Detectors 3/4/2024 Approved KEVIN SARGSYAN