5005 S COOLIDGE AVE 90230

Certificate Information: 5005 S COOLIDGE AVE 90230

Application / Permit
21010-30000-05308
Plan Check / Job No.
B21WL04459
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new S.F.D. w/ 2-car garage and roof trusses
Permit Issued
Issued on 2/25/2022
Issuing Office
Current Status
CofO Issued on 3/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 FELIPE HERNANDEZ
Corrections Issued 10/26/2021 FELIPE HERNANDEZ
Quality Review Completed 11/3/2021 TARIK SAOUD
Building Plans Picked Up 11/5/2021 APPLICANT
Plan Check Approved 2/18/2022 FELIPE HERNANDEZ
Issued 2/25/2022 APPLICANT
CofO in Progress 3/17/2023 JESUS RODRIGUEZ
Permit Finaled 3/22/2023 DANIEL ORRANTE
CofO Issued 3/22/2023 DANIEL ORRANTE
Permit Finaled 3/22/2023 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 12/14/2021 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 12/20/2021 TRACY TATE
Permit Cleared 12/20/2021 TRACY TATE
Roof/Waste drainage to street Cleared 12/20/2021 TRACY TATE
Sewer availability Cleared 12/20/2021 TRACY TATE
Trees in Parkway Cleared 12/21/2021 ADALBERTO VERA
Specific Plan Cleared 12/22/2021 EDUARDO HERMOSO
Hydrant and Access approval Cleared 2/3/2022 KURT CORRAL

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/20/2022 Conditional Approval PATRICK QUALEY
Excavation/Setback/Form/Re-Bar 5/3/2022 Approved PATRICK QUALEY
Footing/Foundation/Slab 5/3/2022 Approved PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Partial Approval PATRICK QUALEY
HVAC-Rough 7/8/2022 Approved EVAN COOPER
PLUMBING-Rough 7/14/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Conditional Approval JESUS RODRIGUEZ
Shower Pan 7/20/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/21/2022 Conditional Approval HERBERT GIRON
Shower Pan 7/21/2022 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 8/25/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 8/26/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 9/8/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/23/2022 Approved JESUS RODRIGUEZ
Green Building Rough 9/23/2022 Approved JESUS RODRIGUEZ
MERV13>=Rough 9/23/2022 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 9/23/2022 Approved JESUS RODRIGUEZ
Insulation 10/5/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 10/26/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 10/26/2022 Approved HERBERT GIRON
ELECTRICAL-Final 1/5/2023 Conditional Approval JESUS RODRIGUEZ
PLUMBING-Final 1/5/2023 Approved JESUS RODRIGUEZ
Gas Test 1/18/2023 Approved JESUS RODRIGUEZ
HVAC-Final 1/18/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/18/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 2/9/2023 Approved JESUS RODRIGUEZ
Final 2/21/2023 Not Ready for Inspection HERBERT GIRON
Green Building Final 2/21/2023 Not Ready for Inspection HERBERT GIRON
MERV13>=Final 2/21/2023 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 2/21/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 3/16/2023 Approved JESUS RODRIGUEZ
Final 3/16/2023 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 3/16/2023 Approved JESUS RODRIGUEZ
MERV13>=Final 3/16/2023 Approved JESUS RODRIGUEZ
Smoke Detectors 3/16/2023 Approved JESUS RODRIGUEZ