5932 N LEMP AVE 1-2 91601
Certificate Information: 5932 N LEMP AVE 1-2 91601
- Application / Permit
- 21010-30000-05090
- Plan Check / Job No.
- B21WL04319
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED ACCESSORY DWELLING UNIT PER ORDINANCE, EQUIPPED THROUGHOUT WITH NFPA-13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | SERGIO SILVA |
| Corrections Issued | 11/3/2021 | SERGIO SILVA |
| Quality Review Completed | 11/15/2021 | TARIK SAOUD |
| Building Plans Picked Up | 11/18/2021 | APPLICANT |
| Plan Check Approved | 2/2/2022 | SERGIO SILVA |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 4/20/2023 | JACK KARGODORIAN |
| Permit Finaled | 4/24/2023 | MICHAEL SMITH |
| CofO Issued | 4/24/2023 | MICHAEL SMITH |
| Permit Finaled | 4/24/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2021 | CARLOS AGUILERA |
| CPC | Cleared | 11/30/2021 | RICHARD REASER |
| CPC | Cleared | 11/30/2021 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/6/2021 | CARLOS AGUILERA |
| Permit | Cleared | 12/7/2021 | CARLOS AGUILERA |
| Highway dedication | Cleared | 12/8/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 12/10/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/5/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/16/2022 | JOHN CONNEALLY |
| Green Code | Cleared | 2/2/2022 | SERGIO SILVA |
| Miscellaneous | Cleared | 2/2/2022 | SERGIO SILVA |
| Miscellaneous | Cleared | 2/2/2022 | SERGIO SILVA |
| Trees in Parkway | Cleared | 3/1/2022 | ADALBERTO VERA |
Contact Information
| Architect | , ; Lic. No.: C35150 | , |
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/10/2022 | Partial Approval | DAVID MATSON |
| Footing/Foundation/Slab | 3/17/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Conditional Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 9/23/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/28/2022 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 9/28/2022 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/29/2022 | Not Ready for Inspection | DAVID MATSON |
| Green Building Rough | 9/29/2022 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Rough | 9/29/2022 | Not Ready for Inspection | DAVID MATSON |
| Verify Sprinkler Sign Off | 9/29/2022 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 10/7/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/7/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 10/18/2022 | Approved | JACK KARGODORIAN |
| Insulation | 10/28/2022 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 11/3/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/21/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 11/21/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/21/2022 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/23/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 12/23/2022 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/30/2022 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 12/30/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 4/17/2023 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 4/17/2023 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 4/17/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/18/2023 | Approved | JACK KARGODORIAN |
| Final | 4/18/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/18/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 4/18/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2023 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 4/18/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 4/18/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 4/20/2023 | Approved | JACK KARGODORIAN |
| Final | 4/20/2023 | OK to Issue CofO | JACK KARGODORIAN |
| HVAC-Final | 4/20/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 4/20/2023 | Approved | JACK KARGODORIAN |
| Service/Power Release | 4/20/2023 | Approved | JACK KARGODORIAN |