2650 N BENEDICT CANYON DR 90210

Certificate Information: 2650 N BENEDICT CANYON DR 90210

Application / Permit
21010-30000-05089
Plan Check / Job No.
B21WL04317
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) ALQ with attached garage.
Permit Issued
Issued on 4/19/2022
Issuing Office
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 JAHANSHAH POURHASSAN
Corrections Issued 10/20/2021 JAHANSHAH POURHASSAN
Quality Review Completed 11/1/2021 TARIK SAOUD
Building Plans Picked Up 11/3/2021 APPLICANT
Applicant returned to address corrections 12/22/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 12/23/2021 JAHANSHAH POURHASSAN
Plan Check Approved 4/18/2022 JAHANSHAH POURHASSAN
Issued 4/19/2022 APPLICANT
CofO in Progress 9/7/2023 MICHAEL PELHAM
Permit Finaled 9/21/2023 DANIEL ORRANTE
CofO Issued 9/21/2023 DANIEL ORRANTE
Permit Finaled 9/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 11/12/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/16/2021 DINAH GARIN
Low Impact Development Cleared 12/14/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 1/11/2022 DINAH GARIN
Hydrant and Access approval Cleared 2/12/2022 RUEL COLE

Contact Information

Contractor S And A Fox Development Inc; Lic. No.: 969587-B 22231 MULHOLLAND HWY #117      CALABASAS, CA 91302
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2022 Approved GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/26/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 6/1/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 6/10/2022 Approved MICHAEL PELHAM
PLUMBING-Rough 6/13/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 6/16/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 6/16/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 6/17/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 6/22/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 6/22/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 6/27/2022 Approved BRENDAN LOONEY
Deputy Reinf. Concrete 6/29/2022 Conditional Approval MICHAEL PELHAM
FLOOD-Proofing Certificate 8/2/2022 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 8/2/2022 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 8/2/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 8/23/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/23/2022 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 8/23/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 10/3/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 10/3/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 10/4/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 10/4/2022 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 10/13/2022 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 10/13/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 10/20/2022 Approved CARLOS MATAMOROS
Drywall Nailing 10/20/2022 Approved CARLOS MATAMOROS
Insulation 10/25/2022 Approved JUAN VALENZUELA
PLUMBING-Final 2/16/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 2/21/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 2/22/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 2/22/2023 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 3/13/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 3/28/2023 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 3/28/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 3/30/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 3/30/2023 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Final 3/30/2023 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Service/Power Release 3/30/2023 Not Required GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 3/30/2023 Approved GERMAN RODRIGUEZ MENDOZA
Structural Steel Frame 3/30/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 9/7/2023 OK to Issue CofO MICHAEL PELHAM