2766 S MANNING AVE 90064

Certificate Information: 2766 S MANNING AVE 90064

Application / Permit
21010-30000-04934
Plan Check / Job No.
B21WL04221
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story S.F.R. w/ attached garage and roof truss. Fully equipped with NFPA13D fire sprinklers system.
Permit Issued
Issued on 8/9/2022
Issuing Office
Current Status
CofO Issued on 1/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 ALFREDO JARA
Corrections Issued 10/12/2021 ALFREDO JARA
Quality Review Completed 10/19/2021 TARIK SAOUD
Applicant returned to address corrections 4/21/2022 ALFREDO JARA
Applicant returned to address corrections 5/24/2022 ALFREDO JARA
Applicant returned to address corrections 6/2/2022 ALFREDO JARA
Applicant returned to address corrections 6/8/2022 ALFREDO JARA
Plan Check Approved 8/4/2022 ALFREDO JARA
Issued 8/9/2022 APPLICANT
Building Plans Picked Up 8/10/2022 APPLICANT
CofO in Progress 12/26/2023 KENNETH NAGLE
Permit Finaled 1/5/2024 DANIEL ORRANTE
CofO Issued 1/5/2024 DANIEL ORRANTE
Permit Finaled 1/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Trees in Parkway Cleared 12/9/2021 ADALBERTO VERA
Hydrant and Access approval Cleared 1/24/2022 KURT CORRAL
Low Impact Development Cleared 1/28/2022 NICK RAYGOZA
Permit Cleared 1/29/2022 ANDREW SLUSSER
Roof/Waste drainage to street Cleared 1/29/2022 ANDREW SLUSSER
Eng Process Fee Ord 176,300 Cleared 2/3/2022 DINAH GARIN
Sewer availability Cleared 2/3/2022 DINAH GARIN
Specific Plan Cleared 2/7/2022 EDUARDO HERMOSO
Flood clearance Cleared 3/22/2022 TIFFANY WONG
Excavation more than 5-ft deep Cleared 8/4/2022 CALOSHA APPROVED
GPI Written Notices Cleared 8/4/2022 ALFREDO JARA
Grading Pre-Inspection Cleared 8/4/2022 ALFREDO JARA

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/21/2022 Partial Approval OGANES TARAKHCHYAN
FLOOD-Elevation Certificate 10/17/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/17/2022 Partial Approval OGANES TARAKHCHYAN
Sewer 10/17/2022 Approved OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 10/20/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/10/2022 Partial Approval OGANES TARAKHCHYAN
FLOOD-Elevation Certificate 11/30/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/30/2022 Partial Approval OGANES TARAKHCHYAN
FLOOD-Elevation Certificate 12/9/2022 Not Ready for Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 12/9/2022 Corrections Issued STEPHANIE SWANSON
FLOOD-Elevation Certificate 12/13/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/13/2022 Partial Approval OGANES TARAKHCHYAN
Wood Frame 1/5/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 2/16/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 2/22/2023 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 2/22/2023 Conditional Approval ASHLEY THOMPSON
Shower Pan 2/22/2023 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 3/2/2023 Not Ready for Inspection CLAYTON GRAHAM
HVAC-Rough 3/2/2023 Approved CLAYTON GRAHAM
Gas Test 3/8/2023 Partial Approval HERBERT GIRON
Shower Pan 3/8/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 3/9/2023 Approved ASHLEY THOMPSON
PLUMBING-Rough 3/9/2023 Conditional Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 3/14/2023 Corrections Issued ASHLEY THOMPSON
FLOOD-Proofing Certificate 3/14/2023 Corrections Issued ASHLEY THOMPSON
Green Building Rough 3/14/2023 Not Ready for Inspection ASHLEY THOMPSON
Special/Order Compliance 3/14/2023 Partial Inspection JESUS PINEDA
Verify Sprinkler Sign Off 3/14/2023 Approved ASHLEY THOMPSON
Wood Frame 3/14/2023 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 3/29/2023 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 4/10/2023 Corrections Issued ASHLEY THOMPSON
FLOOD-Proofing Certificate 4/10/2023 Not Ready for Inspection ASHLEY THOMPSON
Green Building Rough 4/10/2023 Not Ready for Inspection ASHLEY THOMPSON
Deputy Wood Construction 4/12/2023 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 4/18/2023 Not Ready for Inspection JEREMY TODD
FLOOD-Proofing Certificate 4/18/2023 Not Ready for Inspection JEREMY TODD
Green Building Rough 4/18/2023 Not Ready for Inspection JEREMY TODD
Interior/Exterior Lathing 4/19/2023 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 4/27/2023 Conditional Approval CLAYTON GRAHAM
FLOOD-Proofing Certificate 4/27/2023 Approved CLAYTON GRAHAM
Green Building Final 4/27/2023 Corrections Issued CLAYTON GRAHAM
Green Building Rough 4/27/2023 Approved CLAYTON GRAHAM
Insulation 4/27/2023 Not Ready for Inspection CLAYTON GRAHAM
Insulation 5/1/2023 Approved CLAYTON GRAHAM
Drywall Nailing 5/9/2023 Not Ready for Inspection MICHAEL PELHAM
Interior/Exterior Lathing 5/9/2023 Approved MICHAEL PELHAM
Drywall Nailing 5/11/2023 Approved CLAYTON GRAHAM
ELECTRICAL-Final 8/30/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Final 9/5/2023 Corrections Issued CLAYTON GRAHAM
Gas Test 9/19/2023 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 9/19/2023 Corrections Issued BEN MOLSTAD
Gas Test 9/25/2023 Approved TEMISTOCLES CAAL
PLUMBING-Final 9/25/2023 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 9/26/2023 Partial Approval TEMISTOCLES CAAL
PLUMBING-Final 9/27/2023 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 10/3/2023 Approved BEN MOLSTAD
ELECTRICAL-Final 10/20/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 10/27/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Final 10/31/2023 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 11/3/2023 Approved STEPHANIE SWANSON
Deputy Drilled-In Anchors 11/6/2023 Conditional Approval MICHAEL PELHAM
Green Building Final 11/8/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 11/9/2023 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 11/13/2023 Approved STEPHANIE SWANSON
Service/Power Release 11/14/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 11/29/2023 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/29/2023 Partial Approval OGANES TARAKHCHYAN
FLOOD-Elevation Certificate 12/19/2023 Not Ready for Inspection JESUS RODRIGUEZ
Final 12/19/2023 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 12/19/2023 Conditional Approval JESUS RODRIGUEZ
FLOOD-Elevation Certificate 12/26/2023 Approved OGANES TARAKHCHYAN
Final 12/26/2023 OK to Issue CofO OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/26/2023 Approved OGANES TARAKHCHYAN