331 3/4 E 52ND ST 90011
Certificate Information: 331 3/4 E 52ND ST 90011
- Application / Permit
- 21010-30000-04904
- Plan Check / Job No.
- B21WL04185
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) one story ADU Per WFPP Per GCS 65852.2 (e)(1)(D) ann LAMC 12.22 A.33(c)(d) and (g)
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Current Status
- CofO Issued on 1/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2021 | KHUONG TRUONG |
| Corrections Issued | 10/5/2021 | KHUONG TRUONG |
| Plan Check Approved | 6/6/2022 | EDWIN ESPIN |
| Issued | 6/23/2022 | APPLICANT |
| Building Plans Picked Up | 6/30/2022 | APPLICANT |
| CofO in Progress | 1/20/2023 | BRENDAN MORELLI |
| Permit Finaled | 1/24/2023 | RONALD MYRICK |
| CofO Issued | 1/24/2023 | RONALD MYRICK |
| Permit Finaled | 1/24/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2021 | PAMELA TENEZA |
| Sewer availability | Cleared | 10/27/2021 | PAMELA TENEZA |
| Low Impact Development | Cleared | 5/16/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/17/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 7/18/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/26/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 7/27/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/25/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/25/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/25/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 8/30/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/30/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/30/2022 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 8/30/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 9/7/2022 | Approved | RYAN SALAZAR |
| HVAC-Rough | 9/7/2022 | Approved | RYAN SALAZAR |
| Insulation | 9/7/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/9/2022 | Approved | RYAN SALAZAR |
| Service/Power Release | 10/7/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 10/20/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 10/20/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/20/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 10/20/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 10/20/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/20/2022 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 10/20/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 10/20/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/1/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/1/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 11/1/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/1/2022 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 11/1/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/1/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/1/2022 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 11/2/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/2/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 11/14/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 11/14/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 11/23/2022 | Not Ready for Inspection | JULIAN AMAYA |
| Service/Power Release | 11/23/2022 | Not Ready for Inspection | JULIAN AMAYA |
| ELECTRICAL-Final | 1/9/2023 | Approved | BRENDAN MORELLI |
| Final | 1/9/2023 | OK to Issue CofO | BRENDAN MORELLI |
| Service/Power Release | 1/9/2023 | Approved | BRENDAN MORELLI |