2700 N FLETCHER DR 90039

Certificate Information: 2700 N FLETCHER DR 90039

Application / Permit
21010-30000-04830
Plan Check / Job No.
B21WL04099
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story SFD (Unit I) (1,825 sf) (5 bed ; 5 bath) w./ att. 2-car carport (495 sf)
Permit Issued
Issued on 7/14/2023
Issuing Office
Current Status
CofO Issued on 6/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Disabled Access Plans Picked Up 10/4/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 REZA HAGHIGHAT
Corrections Issued 10/10/2021 REZA HAGHIGHAT
Quality Review Completed 10/21/2021 TARIK SAOUD
Applicant returned to address corrections 8/12/2022 REZA HAGHIGHAT
Applicant returned to address corrections 8/26/2022 REZA HAGHIGHAT
Plan Check Approved 9/4/2022 REZA HAGHIGHAT
Building Plans Picked Up 9/6/2022 APPLICANT
Issued 7/14/2023 APPLICANT
CofO in Progress 6/14/2025 NICHOLAS LOPEZ
CofO Issued 6/16/2025 DEROLD HAUFF
Permit Finaled 6/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/30/2021 STEVE MELGAR
"Q" conditions Cleared 11/17/2021 RUBEN VASQUEZ
Prkng lot landscape/Water mgmt Cleared 11/17/2021 RUBEN VASQUEZ
Frnt yard landscape/Water mgmt Cleared 11/18/2021 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 11/18/2021 RUBEN VASQUEZ
ZI Cleared 11/18/2021 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 11/24/2021 STEVE MELGAR
Sewer availability Cleared 11/24/2021 STEVE MELGAR
Highway dedication Cleared 12/9/2021 STEVE MELGAR
Hydrant and Access approval Cleared 1/26/2022 JOHN CONNEALLY
Trees in Parkway Cleared 4/8/2022 ADALBERTO VERA
Permit Cleared 5/5/2022 ALBERT TAM
Low Impact Development Cleared 6/29/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/30/2022 STEVE MELGAR
DAS Clearance Cleared 7/14/2022 REZA HAGHIGHAT
Public Works-Open Permits Cleared 4/24/2025 JERMAINE BAYLARK

Contact Information

Architect , ; Lic. No.: C35150 2355 WESTWOOD BLVD # 900      LOS ANGELES, CA 90064
Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/14/2023 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/11/2023 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 9/12/2023 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 4/23/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/30/2024 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 4/30/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/6/2024 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 5/10/2024 Corrections Issued THOMAS LOGRASSO
Green Building Rough 5/10/2024 Approved THOMAS LOGRASSO
MERV13>=Rough 5/10/2024 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 5/10/2024 Approved THOMAS LOGRASSO
Insulation 6/14/2024 Conditional Approval THOMAS LOGRASSO
Shower Pan 6/14/2024 Approved THOMAS LOGRASSO
Drywall Nailing 8/7/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 8/7/2024 Conditional Approval THOMAS LOGRASSO
Pre-Inspection 1/7/2025 Partial Inspection THOMAS LOGRASSO
ELECTRICAL-Final 3/13/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Final 3/13/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 4/15/2025 Approved NICHOLAS LOPEZ
HVAC-Final 4/15/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 6/13/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 6/13/2025 Approved NICHOLAS LOPEZ
Final 6/13/2025 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 6/13/2025 Approved NICHOLAS LOPEZ
MERV13>=Final 6/13/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Approved NICHOLAS LOPEZ
Service/Power Release 6/13/2025 Not Required NICHOLAS LOPEZ