- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- CofO Issued on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | TARIK SAOUD |
| Corrections Issued | 10/3/2021 | TARIK SAOUD |
| Quality Review Completed | 10/7/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 3/10/2022 | TARIK SAOUD |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Plan Check Approved | 4/1/2022 | TARIK SAOUD |
| Issued | 4/25/2022 | APPLICANT |
| CofO in Progress | 1/24/2024 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 1/27/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
| CofO Issued | 2/1/2024 | DEROLD HAUFF |
| Permit Finaled | 2/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 2/28/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 3/24/2022 | CINDY QI |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/12/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 7/12/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/15/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/15/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 1/24/2023 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/1/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Deputy Wood Construction | 2/13/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Partial Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 4/5/2023 | Conditional Approval | BRENDAN MORELLI |
| Green Building Rough | 4/5/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/24/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Rough | 4/24/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 4/24/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 5/1/2023 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 5/22/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 11/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/10/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/23/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/26/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |