730 N ORANGE DR 90038

Certificate Information: 730 N ORANGE DR 90038

Application / Permit
21010-30000-04772
Plan Check / Job No.
B21WL04057
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-story detached ADU. PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 3/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 ALFREDO JARA
Corrections Issued 10/4/2021 ALFREDO JARA
Quality Review Completed 10/15/2021 TARIK SAOUD
Applicant returned to address corrections 12/20/2021 ALFREDO JARA
Applicant returned to address corrections 1/4/2022 ALFREDO JARA
Applicant returned to address corrections 2/15/2022 ALFREDO JARA
Plan Check Approved 2/22/2022 ALFREDO JARA
Issued 3/2/2022 APPLICANT
CofO in Progress 3/15/2023 BRIAN SULLIVAN
Permit Finaled 3/23/2023 DEROLD HAUFF
CofO Issued 3/23/2023 DEROLD HAUFF
Permit Finaled 3/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 1/3/2022 KHAING AYE
Address approval Cleared 1/4/2022 CINDY QI
Roof/Waste drainage to street Cleared 1/4/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/5/2022 CINDY QI
Sewer availability Cleared 1/5/2022 CINDY QI
Construction near power lines Cleared 1/7/2022 RIDWAN HARDY
Construction within easement Cleared 1/7/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 1/20/2022 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/7/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 4/15/2022 Partial Approval BRIAN SULLIVAN
Deputy Methane Barrier 4/20/2022 Conditional Approval ALIZAH MAYAGOITIA
METHANE-Subgrade 4/21/2022 Approved ALIZAH MAYAGOITIA
Deputy Methane Barrier 4/22/2022 Conditional Approval BRIAN SULLIVAN
METHANE-Barrier 4/25/2022 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/28/2022 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 8/24/2022 Approved STUART CHAPMAN
HVAC-Rough 8/24/2022 Corrections Issued STUART CHAPMAN
METHANE-Rough 8/24/2022 Approved STUART CHAPMAN
PLUMBING-Rough 8/24/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 9/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 9/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 9/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 9/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/12/2022 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 9/12/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 9/12/2022 Conditional Approval JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 9/12/2022 Approved JOAQUIN GREENOUGH
Shower Pan 9/16/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 9/16/2022 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/21/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Insulation 9/21/2022 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/21/2022 Partial Approval JOAQUIN GREENOUGH
Shower Pan 9/21/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 9/21/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 9/21/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/27/2022 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Approved JOAQUIN GREENOUGH
Insulation 9/27/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 9/27/2022 Approved JOAQUIN GREENOUGH
Wood Frame 9/27/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 10/3/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 10/19/2022 Approved BRIAN SULLIVAN
Gas Test 1/9/2023 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 1/20/2023 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Final 2/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 2/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 2/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 2/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 2/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 2/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 2/24/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 3/14/2023 OK to Issue CofO BRIAN SULLIVAN
Footing/Foundation/Slab 3/14/2023 Approved BRIAN SULLIVAN
Green Building Final 3/14/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 3/14/2023 Approved BRIAN SULLIVAN
Smoke Detectors 3/14/2023 Approved BRIAN SULLIVAN