636 N WALTHER WAY 90049
Certificate Information: 636 N WALTHER WAY 90049
- Application / Permit
- 21010-30000-04732
- Plan Check / Job No.
- B21WL04038
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- new construction of one story accessory building (pool house)
- Permit Issued
- Issued on 10/25/2022
- Issuing Office
- Current Status
- CofO Issued on 4/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 10/6/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 10/18/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 7/6/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 8/10/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 8/16/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 9/6/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 10/17/2022 | CHIHARU SUZUKI |
| Issued | 10/25/2022 | APPLICANT |
| Building Plans Picked Up | 10/26/2022 | APPLICANT |
| CofO in Progress | 4/3/2025 | KEVIN SARGSYAN |
| Permit Finaled | 4/10/2025 | RICHARD STEINBACH |
| CofO Issued | 4/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/28/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/28/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/28/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/28/2021 | DINAH GARIN |
| Sewer availability | Cleared | 10/28/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 1/22/2022 | RUEL COLE |
| Miscellaneous | Cleared | 1/28/2022 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 2/2/2022 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 3/3/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/14/2022 | JENSON LEE |
| Excavation more than 5-ft deep | Cleared | 8/10/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 8/10/2022 | FELIPE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 8/10/2022 | FELIPE HERNANDEZ |
Contact Information
| Architect | Schoeplein,, Marc; Lic. No.: C24842 | 960 BLUEGRASS WAY LOS ANGELES, CA 90049 |
| Contractor | Basix Designs & Remodeling Inc; Lic. No.: 769443-B | 650 S HIGHLAND AVE LOS ANGELES, CA 90036 |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 600 WILSHIRE BLVD 760 LOS ANGELES, CA 90017 |
| Engineer | Lund,, Tracy Stephen; Lic. No.: C52531 | 511 W GRAND AVE EL SEGUNDO, CA 90245 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/16/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/20/2023 | Corrections Issued | KENNETH NAGLE |
| Masonry Wall/Backfill | 9/22/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/25/2023 | Partial Approval | ARAM AVEDISIAN |
| Reinforced Concrete Frame | 11/2/2023 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/17/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/17/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 11/21/2023 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 1/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 1/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/29/2024 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 1/29/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/29/2024 | Approved | KEVIN SARGSYAN |
| Shower Pan | 1/29/2024 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 1/29/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 2/16/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/16/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/16/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 2/16/2024 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 2/28/2024 | Approved | KEVIN SARGSYAN |
| Insulation | 2/28/2024 | Approved | KEVIN SARGSYAN |
| Final | 3/4/2025 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 3/4/2025 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/4/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 3/4/2025 | Not Required | KEVIN SARGSYAN |
| Smoke Detectors | 3/4/2025 | Approved | KEVIN SARGSYAN |
| Final | 4/3/2025 | OK to Issue CofO | KEVIN SARGSYAN |