7306-7306 1/2 N INDEPENDENCE AVE 91303

Certificate Information: 7306-7306 1/2 N INDEPENDENCE AVE 91303

Application / Permit
21010-30000-04714
Plan Check / Job No.
B21WL04017
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
new 3-story Duplex B w/ attached 4 car garage (rear) *** 2 of 2 ***
Permit Issued
Issued on 3/3/2022
Issuing Office
Current Status
CofO Corrected on 5/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 HOOMAN HAJIZADEH
Corrections Issued 10/14/2021 HOOMAN HAJIZADEH
Quality Review Completed 10/25/2021 TARIK SAOUD
Applicant returned to address corrections 1/28/2022 HOOMAN HAJIZADEH
Plan Check Approved 2/9/2022 HOOMAN HAJIZADEH
Building Plans Picked Up 2/11/2022 APPLICANT
Issued 3/3/2022 APPLICANT
CofO in Progress 5/4/2023 ALEXANDER HANDY
Re-Activate Permit 5/22/2023 JOHN JANSON
CofO Issued-Status Void 5/22/2023 JOHN JANSON
Permit Finaled-Status Void 5/22/2023 JOHN JANSON
Permit Finaled 5/22/2023 JOHN JANSON
CofO Corrected 5/22/2023 JOHN JANSON
Permit Finaled 5/22/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/19/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/19/2021 LEE GUILBEAUX
Sewer availability Cleared 10/21/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/1/2021 LEE GUILBEAUX
Low Impact Development Cleared 11/2/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 11/3/2021 LEE GUILBEAUX
Miscellaneous Cleared 11/8/2021 LOUIS ORTEGA
Miscellaneous Cleared 11/8/2021 LOUIS ORTEGA
ZA Case Cleared 11/8/2021 LOUIS ORTEGA
Hydrant and Access approval Cleared 1/16/2022 JOHN CONNEALLY

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/17/2022 Corrections Issued STEVEN BACK
Underground Mechanical 3/17/2022 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 3/25/2022 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 3/25/2022 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 4/26/2022 Approved STEVEN BACK
Footing/Foundation/Slab 4/26/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 7/19/2022 Corrections Issued STEVEN BACK
Deputy Wood Construction 7/19/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 9/16/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 9/16/2022 Approved STEVEN BACK
Gas Test 9/16/2022 Partial Approval STEVEN BACK
Green Building Rough 9/16/2022 Not Ready for Inspection STEVEN BACK
HVAC-Rough 9/16/2022 Approved STEVEN BACK
PLUMBING-Rough 9/16/2022 Not Ready for Inspection STEVEN BACK
Verify Sprinkler Sign Off 9/16/2022 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 9/20/2022 Not Ready for Inspection STEVEN BACK
Green Building Rough 9/20/2022 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 9/20/2022 Corrections Issued STEVEN BACK
Verify Sprinkler Sign Off 9/20/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 9/29/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Corrections Issued STEVEN BACK
Green Building Rough 9/29/2022 Approved STEVEN BACK
Interior/Exterior Lathing 9/29/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 9/29/2022 Corrections Issued STEVEN BACK
Wood Frame 10/5/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/17/2022 Approved STEVEN BACK
Drywall Nailing 10/17/2022 Approved STEVEN BACK
Insulation 10/17/2022 Approved STEVEN BACK
Shower Pan 11/14/2022 Corrections Issued JESUS PINEDA
Shower Pan 11/22/2022 Approved STEVEN BACK
Special/Order Compliance 11/22/2022 Approved ALEXANDER HANDY
Sewer 12/20/2022 Approved ALEXANDER HANDY
Underground Mechanical 12/20/2022 Corrections Issued ALEXANDER HANDY
Sewer 12/23/2022 Approved ALEXANDER HANDY
Underground Mechanical 12/23/2022 Partial Approval ALEXANDER HANDY
Final 4/26/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 4/26/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 4/26/2023 SGSOV Not Ready ALEXANDER HANDY
Service/Power Release 4/26/2023 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 4/26/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 5/3/2023 Approved ALEXANDER HANDY
Final 5/3/2023 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 5/3/2023 Approved ALEXANDER HANDY
PLUMBING-Final 5/3/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved ALEXANDER HANDY
Service/Power Release 5/3/2023 Approved ALEXANDER HANDY