1750-1752 S MARVIN AVE 90019
Certificate Information: 1750-1752 S MARVIN AVE 90019
- Application / Permit
- 21010-30000-04680
- Plan Check / Job No.
- B21WL03942
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- new 2-family dwelling with new 2-car garage and roof trusses
- Permit Issued
- Issued on 2/8/2022
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | TARIK SAOUD |
| Corrections Issued | 9/26/2021 | TARIK SAOUD |
| Quality Review Completed | 9/30/2021 | CHIHARU SUZUKI |
| Plan Check Approved | 2/4/2022 | TARIK SAOUD |
| Issued | 2/8/2022 | APPLICANT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| CofO in Progress | 1/10/2023 | JOSE AVILA |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 10/28/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 11/17/2021 | LONDY ALVARADO |
| Frnt yard landscape/Water mgmt | Cleared | 12/9/2021 | RYAN LY |
| Address approval | Cleared | 12/10/2021 | ABEL CASILLAS |
| Permit | Cleared | 12/10/2021 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 12/10/2021 | ABEL CASILLAS |
| Hydrant and Access approval | Cleared | 12/14/2021 | GREGORY HOERNER |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2021 | ABEL CASILLAS |
| Sewer availability | Cleared | 12/16/2021 | ABEL CASILLAS |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/1/2022 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 3/16/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 3/31/2022 | Approved | JOSE AVILA |
| Deputy Wood Construction | 4/27/2022 | Conditional Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 5/5/2022 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 5/12/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/12/2022 | Corrections Issued | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 5/16/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/25/2022 | Approved | JOSE AVILA |
| Green Building Rough | 5/25/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 5/25/2022 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 5/25/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 5/27/2022 | Approved | JOSE AVILA |
| Insulation | 6/3/2022 | Approved | JOSE AVILA |
| Shower Pan | 6/7/2022 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 6/28/2022 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 7/7/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 9/22/2022 | Partial Inspection | JOSE AVILA |
| HVAC-Final | 9/22/2022 | Partial Inspection | JOSE AVILA |
| PLUMBING-Final | 9/22/2022 | Partial Inspection | JOSE AVILA |
| Service/Power Release | 9/22/2022 | Partial Inspection | JOSE AVILA |
| ELECTRICAL-Final | 10/13/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 10/13/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 10/13/2022 | Approved | JOSE AVILA |
| Service/Power Release | 10/13/2022 | No Access for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 12/2/2022 | Corrections Issued | JOSE AVILA |
| Final | 12/2/2022 | Not Ready for Inspection | JOSE AVILA |
| Green Building Final | 12/2/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 12/2/2022 | Not Ready for Inspection | JOSE AVILA |
| Smoke Detectors | 12/2/2022 | Approved | JOSE AVILA |
| Final | 1/6/2023 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 1/6/2023 | Approved | JOSE AVILA |