1204 N CHICKORY LANE 90049

Certificate Information: 1204 N CHICKORY LANE 90049

Application / Permit
21010-30000-04677
Plan Check / Job No.
B21WL03940
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story S.F.D. w/ 1-level basement and att. 5-car garage at basement
Permit Issued
Issued on 9/1/2022
Issuing Office
Current Status
CofO Issued on 10/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 REZA HAGHIGHAT
Corrections Issued 10/2/2021 REZA HAGHIGHAT
Quality Review Completed 10/18/2021 TARIK SAOUD
Applicant returned to address corrections 4/18/2022 REZA HAGHIGHAT
Applicant returned to address corrections 4/29/2022 REZA HAGHIGHAT
Applicant returned to address corrections 5/12/2022 REZA HAGHIGHAT
Applicant returned to address corrections 8/26/2022 REZA HAGHIGHAT
Plan Check Approved 8/29/2022 REZA HAGHIGHAT
Plan Check Approved 8/31/2022 REZA HAGHIGHAT
Issued 9/1/2022 APPLICANT
Building Plans Picked Up 9/1/2022 APPLICANT
CofO in Progress 10/22/2025 CARLOS MATAMOROS
Permit Finaled 10/22/2025 RICHARD STEINBACH
CofO Issued 10/22/2025 RICHARD STEINBACH
Permit Finaled 10/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/22/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 11/22/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 11/22/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 11/22/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 11/22/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/24/2021 ANTHONY MAINEZ
Hydrant and Access approval Cleared 2/10/2022 KURT CORRAL
Low Impact Development Cleared 2/15/2022 TA ANH
Roof/Waste drainage to street Cleared 4/28/2022 ANTHONY MAINEZ
Excavation more than 5-ft deep Cleared 5/12/2022 CALOSHA APPROVED
GPI Written Notices Cleared 5/12/2022 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 5/12/2022 REZA HAGHIGHAT
Private sewage disp. approval Cleared 8/9/2022 DAN RYAN EVANGELISTA
BHO/Hillside ordinance Cleared 8/29/2022 ANTHONY MAINEZ
Sewer availability Cleared 8/29/2022 ANTHONY MAINEZ

Contact Information

Contractor J A L Inc; Lic. No.: 986943-B 8721 W SUNSET BLVD STE 208      WEST HOLLYWOOD, CA 90069
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Geologist , ; Lic. No.: GEO2673    2165 N MARVEL AVE    SIMI VALLEY, CA 93065

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2022 Approved CARLOS MATAMOROS
Deputy Steel/Welding 10/27/2022 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 11/9/2022 Conditional Approval CARLOS MATAMOROS
Deputy Shotcrete 11/9/2022 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 11/9/2022 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 11/10/2022 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 12/21/2022 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/21/2022 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 12/21/2022 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 12/22/2022 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/3/2023 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 1/3/2023 Partial Inspection CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 1/6/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/31/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 2/1/2023 Conditional Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 2/3/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 2/3/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 2/6/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/21/2023 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 2/21/2023 Partial Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/3/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/17/2023 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/20/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/28/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 3/30/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 4/11/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/11/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 4/17/2023 Approved MICHAEL PELHAM
Footing/Foundation/Slab 4/17/2023 Partial Approval MICHAEL PELHAM
Deputy Shotcrete 4/18/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/21/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/26/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/27/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/5/2023 Conditional Approval CARLOS MATAMOROS
PLUMBING-Rough 5/5/2023 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 5/8/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 5/22/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/22/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/23/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/26/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 6/8/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 6/9/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/13/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 6/14/2023 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 6/14/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 6/15/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/13/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/18/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 7/19/2023 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/19/2023 Partial Approval CARLOS MATAMOROS
Deputy Shotcrete 7/27/2023 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/27/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 9/8/2023 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 10/30/2023 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 11/27/2023 Corrections Issued MICHAEL PELHAM
PLUMBING-Rough 11/28/2023 Partial Approval CARLOS MATAMOROS
Underground Mechanical 11/28/2023 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 1/18/2024 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 1/18/2024 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/18/2024 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/28/2024 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 4/4/2024 Approved CARLOS MATAMOROS
Deputy Wood Construction 4/18/2024 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 6/20/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 6/20/2024 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 6/21/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 6/28/2024 Corrections Issued CARLOS MATAMOROS
Green Building Rough 6/28/2024 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 6/28/2024 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 6/28/2024 Partial Approval CARLOS MATAMOROS
HVAC-Rough 7/15/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 7/16/2024 Approved CARLOS MATAMOROS
Drywall Nailing 7/30/2024 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 7/30/2024 Approved CARLOS MATAMOROS
Drywall Nailing 8/12/2024 Partial Approval CARLOS MATAMOROS
Insulation 8/12/2024 Approved CARLOS MATAMOROS
Drywall Nailing 8/29/2024 Approved CARLOS MATAMOROS
Shower Pan 9/11/2024 Partial Approval CARLOS MATAMOROS
Shower Pan 10/1/2024 Approved CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 12/20/2024 Approved CARLOS MATAMOROS
Underground Mechanical 12/20/2024 Approved CARLOS MATAMOROS
Underground Mechanical 2/11/2025 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/20/2025 Partial Approval CARLOS MATAMOROS
Masonry Wall/Backfill 2/26/2025 Approved CARLOS MATAMOROS
Pre-Inspection 4/9/2025 Approved CARLOS MATAMOROS
Gas Test 4/18/2025 Approved STEPHANIE SWANSON
Service/Power Release 4/21/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Final 6/30/2025 Corrections Issued SEAN HAUPT
HVAC-Final 7/2/2025 Approved BOBBY KEY
ELECTRICAL-Final 7/8/2025 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 7/10/2025 Approved MEL KHACHATOURIAN
PLUMBING-Final 7/14/2025 Not Ready for Inspection MEL KHACHATOURIAN
Service/Power Release 7/17/2025 Approved MICHAEL PELHAM
PLUMBING-Final 7/22/2025 Corrections Issued MEL KHACHATOURIAN
Final 7/29/2025 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 7/29/2025 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Approved TEMISTOCLES CAAL
Gas Test 10/3/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 10/9/2025 Approved CARLOS MATAMOROS
Final 10/9/2025 OK to Issue CofO CARLOS MATAMOROS
Footing/Foundation/Slab 10/9/2025 Approved CARLOS MATAMOROS
Green Building Final 10/9/2025 Approved CARLOS MATAMOROS
Reinforced Concrete Frame 10/9/2025 Approved CARLOS MATAMOROS
Smoke Detectors 10/9/2025 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/9/2025 Approved CARLOS MATAMOROS