11853 W WEIR ST 90230

Certificate Information: 11853 W WEIR ST 90230

Application / Permit
21010-30000-04572
Plan Check / Job No.
B21WL03895
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE (FRONT building)
Permit Issued
Issued on 4/18/2022
Issuing Office
Current Status
CofO Issued on 10/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 TARIK SAOUD
Corrections Issued 9/25/2021 TARIK SAOUD
Quality Review Completed 9/30/2021 CHIHARU SUZUKI
Plan Check Approved 12/2/2021 TARIK SAOUD
Building Plans Picked Up 12/7/2021 APPLICANT
Issued 4/18/2022 APPLICANT
CofO in Progress 9/21/2024 TEMISTOCLES CAAL
Permit Finaled 10/3/2024 RICHARD STEINBACH
CofO Issued 10/3/2024 RICHARD STEINBACH
Permit Finaled 10/3/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/30/2021 RAYMOND MUGAMBWA
Permit Cleared 10/6/2021 RAYMOND MUGAMBWA
Eng Process Fee Ord 176,300 Cleared 10/7/2021 RAYMOND MUGAMBWA
Sewer availability Cleared 10/7/2021 RAYMOND MUGAMBWA
Hydrant and Access approval Cleared 10/13/2021 MATTHEW CRAIG
Specific Plan Cleared 10/14/2021 PEDRO AYALA
Low Impact Development Cleared 11/3/2021 TA ANH
Roof/Waste drainage to street Cleared 11/5/2021 RAYMOND MUGAMBWA
Trees in Parkway Cleared 11/9/2021 ADALBERTO VERA

Contact Information

Contractor 8a General Construction; Lic. No.: 1020625-B 11660 EL GRANADA AVE      LYNWOOD, CA 90262
Engineer Inman,, Donald J; Lic. No.: C11888 5131 FOX HILLS AVENUE      BUENA PARK, CA 90621

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/20/2022 Corrections Issued DAVID FEILER
Underground Mechanical 4/20/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 4/25/2022 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/28/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 4/28/2022 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 5/2/2022 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 5/2/2022 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 5/5/2022 Approved DAVID FEILER
Footing/Foundation/Slab 5/5/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 6/27/2022 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 6/27/2022 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 6/27/2022 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 6/29/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 6/29/2022 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 6/29/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 10/20/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 10/20/2022 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/20/2022 Not Ready for Inspection HERBERT GIRON
Green Building Rough 10/20/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 10/20/2022 Not Ready for Inspection HERBERT GIRON
MERV13>=Rough 10/20/2022 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 10/20/2022 Approved HERBERT GIRON
Verify Sprinkler Sign Off 10/20/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 10/24/2022 Approved HERBERT GIRON
HVAC-Rough 10/24/2022 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 10/27/2022 Approved HERBERT GIRON
Shower Pan 10/27/2022 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Corrections Issued HERBERT GIRON
HVAC-Final 10/31/2022 Not Ready for Inspection HERBERT GIRON
Shower Pan 10/31/2022 Not Ready for Inspection HERBERT GIRON
Wood Frame 10/31/2022 Not Ready for Inspection HERBERT GIRON
Deputy Wood Construction 11/1/2022 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Not Ready for Inspection HERBERT GIRON
Shower Pan 11/15/2022 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Approved HERBERT GIRON
Shower Pan 11/21/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 11/23/2022 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 12/2/2022 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 12/12/2022 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 12/19/2022 No Access for Inspection JESUS RODRIGUEZ
Final 12/19/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 12/19/2022 No Access for Inspection JESUS RODRIGUEZ
MERV13>=Rough 12/19/2022 No Access for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 12/19/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/29/2022 Corrections Issued DAVID FEILER
Green Building Rough 12/29/2022 Not Ready for Inspection DAVID FEILER
MERV13>=Rough 12/29/2022 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 1/3/2023 Corrections Issued HERBERT GIRON
Green Building Rough 1/3/2023 Approved HERBERT GIRON
MERV13>=Rough 1/3/2023 Approved HERBERT GIRON
Verify Sprinkler Sign Off 1/3/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/30/2023 Conditional Approval HERBERT GIRON
Wood Frame 1/30/2023 Conditional Approval HERBERT GIRON
Final 2/9/2023 Corrections Issued HERBERT GIRON
Insulation 2/9/2023 Approved HERBERT GIRON
Drywall Nailing 3/16/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 3/16/2023 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 4/13/2023 Approved HERBERT GIRON
Underground Mechanical 8/28/2023 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 4/29/2024 Corrections Issued TEMISTOCLES CAAL
Final 4/29/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 4/29/2024 Corrections Issued TEMISTOCLES CAAL
MERV13>=Final 4/29/2024 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Not Ready TEMISTOCLES CAAL
Service/Power Release 4/29/2024 Corrections Issued TEMISTOCLES CAAL
Smoke Detectors 4/29/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 8/1/2024 Corrections Issued TEMISTOCLES CAAL
Final 8/1/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 8/1/2024 Corrections Issued TEMISTOCLES CAAL
MERV13>=Final 8/1/2024 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Not Ready TEMISTOCLES CAAL
Service/Power Release 8/1/2024 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 8/23/2024 Approved TEMISTOCLES CAAL
Final 8/23/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 8/23/2024 Approved TEMISTOCLES CAAL
MERV13>=Final 8/23/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Not Ready TEMISTOCLES CAAL
Service/Power Release 8/23/2024 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Not Ready TEMISTOCLES CAAL
Final 9/20/2024 OK to Issue CofO TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 9/20/2024 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 9/20/2024 Approved TEMISTOCLES CAAL