1615 N CORONADO ST 90026
Certificate Information: 1615 N CORONADO ST 90026
- Application / Permit
- 21010-30000-04442
- Plan Check / Job No.
- B21WL03825
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New detached garage *** 2 of 2 ***
- Permit Issued
- Issued on 8/17/2022
- Issuing Office
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 9/20/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 9/30/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 2/18/2022 | FELIPE HERNANDEZ |
| Plan Check Approved | 8/15/2022 | FELIPE HERNANDEZ |
| Issued | 8/17/2022 | APPLICANT |
| Building Plans Picked Up | 8/24/2022 | APPLICANT |
| CofO in Progress | 4/25/2025 | HAMIK HARTOUNIAN |
| No Progress | 4/27/2025 | DEROLD HAUFF |
| CofO in Progress | 4/27/2025 | DEROLD HAUFF |
| CofO Issued | 5/7/2025 | DEROLD HAUFF |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 10/28/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 11/19/2021 | JONATAN VELASQUEZ |
| Hydrant and Access approval | Cleared | 1/10/2022 | GILBERT URREA |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 1/20/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2022 | CELINA MORENO |
| Permit | Cleared | 1/20/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 2/7/2022 | CELINA MORENO |
| GPI Written Notices | Cleared | 8/15/2022 | FELIPE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 8/15/2022 | FELIPE HERNANDEZ |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/17/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/3/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 3/7/2023 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/28/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Reinf. Concrete | 5/26/2023 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 6/12/2023 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/12/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/10/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 10/10/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 10/10/2023 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 10/25/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 3/27/2024 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 8/13/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/23/2024 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 10/2/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/24/2024 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/25/2024 | Approved | LUIS CASTRO |
| Service/Power Release | 12/13/2024 | Partial Inspection | LUIS CASTRO |
| Final | 4/3/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/3/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 4/3/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Not Required | HAMIK HARTOUNIAN |
| Service/Power Release | 4/3/2025 | Not Required | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/3/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 4/17/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 4/25/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |