1601 N CORONADO ST 90026

Certificate Information: 1601 N CORONADO ST 90026

Application / Permit
21010-30000-04440
Plan Check / Job No.
B21WL03823
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-story Duplex with attached garage. Fully equipped with fire sprinkler system NFPA13D
Permit Issued
Issued on 12/2/2022
Issuing Office
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 ALFREDO JARA
Corrections Issued 9/21/2021 ALFREDO JARA
Quality Review Completed 10/1/2021 TARIK SAOUD
Applicant returned to address corrections 3/1/2022 ALFREDO JARA
Applicant returned to address corrections 4/7/2022 CHIHARU SUZUKI
Applicant returned to address corrections 5/11/2022 ALFREDO JARA
Building Plans Picked Up 5/12/2022 APPLICANT
Applicant returned to address corrections 5/20/2022 ALFREDO JARA
Applicant returned to address corrections 7/19/2022 ALFREDO JARA
Applicant returned to address corrections 8/9/2022 ALFREDO JARA
Plan Check Approved 10/11/2022 ALFREDO JARA
No Progress 10/11/2022 ALFREDO JARA
Plan Check Approved 11/28/2022 ALFREDO JARA
Issued 12/2/2022 APPLICANT
CofO in Progress 4/22/2026 HAMIK HARTOUNIAN
Permit Finaled 4/23/2026 DEROLD HAUFF
CofO Issued 4/23/2026 DEROLD HAUFF
Permit Finaled 4/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 11/9/2021 TA ANH
Address approval Cleared 12/22/2021 CELINA MORENO
Address approval Cleared 12/22/2021 CELINA MORENO
Highway dedication Cleared 12/22/2021 CELINA MORENO
Permit Cleared 12/22/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/27/2021 CELINA MORENO
Sewer availability Cleared 12/27/2021 CELINA MORENO
Hydrant and Access approval Cleared 1/10/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 1/14/2022 CELINA MORENO
Trees in Parkway Cleared 2/3/2022 ADALBERTO VERA
Excavation more than 5-ft deep Cleared 5/31/2022 CALOSHA APPROVED
GPI Written Notices Cleared 5/31/2022 ALFREDO JARA
Grading Pre-Inspection Cleared 5/31/2022 ALFREDO JARA

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2024 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 5/16/2024 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/20/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 5/21/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/3/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 6/7/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/21/2024 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/5/2024 Partial Approval HAMIK HARTOUNIAN
Sewer 8/5/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Sewer 8/8/2024 Approved BRENDAN MORELLI
Footing/Foundation/Slab 8/16/2024 Partial Approval WILLIAM SIERRA
Footing/Foundation/Slab 8/30/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 9/3/2024 Conditional Approval HAMIK HARTOUNIAN
Underground Mechanical 9/23/2024 Approved LUIS CASTRO
Footing/Foundation/Slab 9/26/2024 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Wood Construction 11/27/2024 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Partial Approval LUIS CASTRO
Deputy Wood Construction 12/16/2024 Conditional Approval JOSH MEISTER
Deputy Wood Construction 12/18/2024 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 12/19/2024 Partial Inspection FREDDIE RIVERA
Deputy Drilled-In Anchors 1/10/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 1/10/2025 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/22/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 1/23/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/28/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/27/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 2/27/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/27/2025 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 2/27/2025 Approved HAMIK HARTOUNIAN
Insulation 3/10/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 3/10/2025 Approved ANTHONY RAMOS
Drywall Nailing 3/19/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 4/14/2025 Approved ALEX COLIN
Shower Pan 4/14/2025 Approved ALEX COLIN
Deputy Reinf. Concrete 6/5/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 6/27/2025 Conditional Approval HAMIK HARTOUNIAN
Service/Power Release 10/29/2025 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 10/30/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Service/Power Release 11/13/2025 Corrections Issued HAMIK HARTOUNIAN
Special/Order Compliance 11/13/2025 Partial Inspection OSVALDO PARAMO
Service/Power Release 11/18/2025 No Access for Inspection FREDDIE RIVERA
ELECTRICAL-Final 11/19/2025 Approved HAMIK HARTOUNIAN
Service/Power Release 11/19/2025 Approved HAMIK HARTOUNIAN
Gas Test 12/10/2025 Not Ready for Inspection SCOTT FINNILA
HVAC-Final 12/10/2025 Corrections Issued SCOTT FINNILA
PLUMBING-Final 12/10/2025 Corrections Issued SCOTT FINNILA
Gas Test 1/9/2026 Approved HAMIK HARTOUNIAN
HVAC-Final 1/9/2026 Approved HAMIK HARTOUNIAN
PLUMBING-Final 1/9/2026 Corrections Issued HAMIK HARTOUNIAN
Smoke Detectors 1/9/2026 Approved HAMIK HARTOUNIAN
Final 3/5/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/5/2026 Approved HAMIK HARTOUNIAN
Green Building Final 3/5/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Not Ready HAMIK HARTOUNIAN
ELECTRICAL-Final 4/20/2026 Approved HAMIK HARTOUNIAN
Final 4/20/2026 OK to Issue CofO HAMIK HARTOUNIAN
HVAC-Final 4/20/2026 Approved HAMIK HARTOUNIAN
PLUMBING-Final 4/20/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/20/2026 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 4/20/2026 Approved HAMIK HARTOUNIAN