1609 N CORONADO ST 90026
Certificate Information: 1609 N CORONADO ST 90026
- Application / Permit
- 21010-30000-04437
- Plan Check / Job No.
- B21WL03821
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New Detached 2-Car Garage **2 of 2**
- Permit Issued
- Issued on 7/12/2022
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | DAVID CASTILLO |
| Corrections Issued | 9/29/2021 | DAVID CASTILLO |
| Quality Review Completed | 10/7/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 4/15/2022 | DAVID CASTILLO |
| Plan Check Approved | 6/18/2022 | DAVID CASTILLO |
| Issued | 7/12/2022 | APPLICANT |
| Building Plans Picked Up | 7/13/2022 | APPLICANT |
| CofO in Progress | 2/23/2026 | HAMIK HARTOUNIAN |
| No Progress | 2/23/2026 | DEROLD HAUFF |
| CofO in Progress | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 3/12/2026 | DEROLD HAUFF |
| CofO Issued | 3/12/2026 | DEROLD HAUFF |
| Permit Finaled | 3/12/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 11/30/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 1/12/2022 | CHRIS VONG |
| BHO/Hillside ordinance | Cleared | 1/13/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/13/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/13/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/13/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/13/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2022 | STEVE MELGAR |
| Permit | Cleared | 1/13/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 1/13/2022 | STEVE MELGAR |
| Frnt yard landscape/Water mgmt | Cleared | 2/3/2022 | DANIEL CORONADO |
| Frnt yard landscape/Water mgmt | Cleared | 2/3/2022 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 2/14/2022 | JOHN CONNEALLY |
| Grading Pre-Inspection | Cleared | 6/16/2022 | DAVID CASTILLO |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | Gomez A Landscaping Designs; Lic. No.: 1011989-C27 | P O BOX 1387 SIMI VALLEY, CA 93062 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Sims,, Bradley Alan; Lic. No.: C58238 | 5462 WINDWARD AVE LONG BEACH, CA 90814 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
| Engineer | Toedter,, Randy Wayne; Lic. No.: C37316 | 7474 EISENHOWER ST VENTURA, CA 93003 |
| Geologist | Rahimikian,, Pedram; Lic. No.: EG2683 | 21414 ARCOS DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/19/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/4/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/12/2023 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/26/2023 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/1/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 2/3/2023 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 9/8/2023 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/12/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/17/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 10/17/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/17/2023 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 10/31/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 3/27/2024 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 9/20/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/2/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 10/29/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 11/13/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 11/18/2025 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 12/4/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 2/3/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/3/2026 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 2/3/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 2/3/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/3/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 2/13/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 2/13/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 2/19/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |