1609 N CORONADO ST 90026

Certificate Information: 1609 N CORONADO ST 90026

Application / Permit
21010-30000-04435
Plan Check / Job No.
B21WL03821
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-Story S.F.D w/Roof Truss ** 1 of 2 **
Permit Issued
Issued on 7/12/2022
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 DAVID CASTILLO
Corrections Issued 9/29/2021 DAVID CASTILLO
Quality Review Completed 10/7/2021 TARIK SAOUD
Applicant returned to address corrections 4/15/2022 DAVID CASTILLO
Plan Check Approved 7/5/2022 DAVID CASTILLO
Issued 7/12/2022 APPLICANT
Building Plans Picked Up 7/13/2022 APPLICANT
CofO in Progress 2/23/2026 HAMIK HARTOUNIAN
Permit Finaled 2/23/2026 DEROLD HAUFF
CofO Issued 2/23/2026 DEROLD HAUFF
Permit Finaled 2/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 1/12/2022 CHRIS VONG
Address approval Cleared 1/13/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 1/13/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 1/13/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 1/13/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 1/13/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 1/13/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/13/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 1/13/2022 STEVE MELGAR
Sewer availability Cleared 1/13/2022 STEVE MELGAR
Frnt yard landscape/Water mgmt Cleared 2/3/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 2/14/2022 JOHN CONNEALLY
Grading Pre-Inspection Cleared 6/16/2022 DAVID CASTILLO

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor Gomez A Landscaping Designs; Lic. No.: 1011989-C27 P O BOX 1387      SIMI VALLEY, CA 93062
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26940 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Sims,, Bradley Alan; Lic. No.: C58238 5462 WINDWARD AVE      LONG BEACH, CA 90814
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003
Engineer Toedter,, Randy Wayne; Lic. No.: C37316 7474 EISENHOWER ST      VENTURA, CA 93003
Geologist Rahimikian,, Pedram; Lic. No.: EG2683 21414 ARCOS DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 10/11/2022 Partial Inspection THOMAS LOGRASSO
PLUMBING-Rough 11/10/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 12/9/2022 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 12/15/2022 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 12/19/2022 Partial Approval THOMAS LOGRASSO
Deputy Reinf. Concrete 12/21/2022 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 1/4/2023 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 1/12/2023 Partial Approval THOMAS LOGRASSO
Deputy Reinf. Concrete 1/13/2023 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 1/26/2023 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 2/1/2023 Partial Approval THOMAS LOGRASSO
Deputy Reinf. Concrete 2/3/2023 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 5/24/2023 Partial Approval THOMAS LOGRASSO
Deputy Reinf. Concrete 5/26/2023 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 6/7/2023 Partial Approval THOMAS LOGRASSO
Underground Mechanical 6/9/2023 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 6/27/2023 Approved THOMAS LOGRASSO
Deputy Wood Construction 7/17/2023 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Corrections Issued THOMAS LOGRASSO
Deputy Wood Construction 7/26/2023 Approved DONALD CRICHLOW
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 9/8/2023 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 9/12/2023 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval THOMAS LOGRASSO
Sewer 9/12/2023 Approved THOMAS LOGRASSO
Underground Mechanical 9/12/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 9/19/2023 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 9/29/2023 Corrections Issued THOMAS LOGRASSO
Shower Pan 9/29/2023 Partial Approval THOMAS LOGRASSO
HVAC-Rough 10/6/2023 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 10/6/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/11/2023 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 10/11/2023 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 10/11/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 10/11/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 10/11/2023 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 10/17/2023 Conditional Approval THOMAS LOGRASSO
Green Building Rough 10/17/2023 Approved THOMAS LOGRASSO
HVAC-Rough 10/17/2023 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 10/17/2023 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 10/17/2023 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 10/17/2023 Approved THOMAS LOGRASSO
Insulation 10/25/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 10/31/2023 Approved THOMAS LOGRASSO
Drywall Nailing 10/31/2023 Approved THOMAS LOGRASSO
HVAC-Rough 10/31/2023 Approved THOMAS LOGRASSO
Insulation 10/31/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 11/7/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Final 3/27/2024 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Final 4/12/2024 Not Ready for Inspection THOMAS LOGRASSO
Deputy Reinf. Masonry 6/21/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 7/3/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 8/20/2024 Conditional Approval FREDDIE RIVERA
Deputy Reinf. Concrete 9/20/2024 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Final 9/23/2024 Approved LUIS CASTRO
ELECTRICAL-Final 9/25/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 10/2/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 10/24/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 10/25/2024 Approved LUIS CASTRO
Deputy Reinf. Concrete 11/6/2024 Conditional Approval HAMIK HARTOUNIAN
Service/Power Release 12/4/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Service/Power Release 12/13/2024 Partial Inspection LUIS CASTRO
Deputy Reinf. Concrete 6/17/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 6/23/2025 Conditional Approval HAMIK HARTOUNIAN
Service/Power Release 11/19/2025 Approved HAMIK HARTOUNIAN
Gas Test 1/9/2026 Approved HAMIK HARTOUNIAN
HVAC-Final 1/9/2026 Approved HAMIK HARTOUNIAN
Smoke Detectors 1/9/2026 Approved HAMIK HARTOUNIAN
Final 2/3/2026 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 2/3/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Approved HAMIK HARTOUNIAN
Final 2/13/2026 Corrections Issued HAMIK HARTOUNIAN
Final 2/19/2026 OK to Issue CofO HAMIK HARTOUNIAN