1719 1/2 N EDGEMONT ST 90027

Certificate Information: 1719 1/2 N EDGEMONT ST 90027

Application / Permit
21010-30000-04403
Plan Check / Job No.
B21WL03794
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story detached ADU (796 sf) with att. 1-car garage and storage (444 sf) and roof deck serving ADU per LAMC 12.22A33 (c) and (d)
Permit Issued
Issued on 12/21/2023
Issuing Office
San Pedro
Current Status
Issued on 12/21/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/26/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 FELIPE HERNANDEZ
Corrections Issued 10/15/2021 FELIPE HERNANDEZ
Quality Review Completed 10/28/2021 TARIK SAOUD
Applicant returned to address corrections 5/31/2022 FELIPE HERNANDEZ
Building Plans Picked Up 5/31/2022 APPLICANT
Plan Check Approved 1/18/2023 REZA HAGHIGHAT
Issued 12/21/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/3/2022 ABEL CASILLAS
Tenant Habitability Plan Cleared 5/4/2022 MICHAEL SOTO
Hydrant and Access approval Cleared 6/1/2022 CINDY JOSSELYN
Low Impact Development Cleared 10/24/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 10/24/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 10/25/2022 ABEL CASILLAS
Sewer availability Cleared 10/26/2022 ABEL CASILLAS
ZI Cleared 12/7/2022 LIKYELESH ABERA
Grading Pre-Inspection Cleared 1/18/2023 FELIPE HERNANDEZ

Contact Information

Contractor Cunanan Voltaire; Lic. No.: 973248-B 22418 RAVENNA AVENUE      CARSON, CA 90745
Engineer Alferez,, Vicente Narvaez; Lic. No.: C53875 460 E CARSON PLAZA DR STE 212      CARSON, CA 90746

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/4/2024 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 3/5/2024 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 3/11/2024 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Approved ENRIQUE MIRELES
Green Building Rough 4/10/2024 Approved ENRIQUE MIRELES
HVAC-Rough 4/10/2024 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 4/10/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/24/2024 Approved ENRIQUE MIRELES
Underground Mechanical 4/26/2024 Partial Approval JOSEPH MCGARRY
Sewer 5/7/2024 Partial Approval JOSEPH MCGARRY
Sewer 5/13/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/19/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 8/19/2024 Approved ENRIQUE MIRELES
Insulation 8/21/2024 Approved ENRIQUE MIRELES
Drywall Nailing 8/26/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 11/13/2024 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Final 11/13/2024 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 11/13/2024 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 11/15/2024 Approved BRENDAN MORELLI
PLUMBING-Final 11/15/2024 Approved BRENDAN MORELLI
Final 3/25/2025 Corrections Issued ENRIQUE MIRELES
Green Building Final 3/25/2025 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/25/2025 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 3/25/2025 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 3/25/2025 Approved ENRIQUE MIRELES
Final 4/15/2025 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 4/15/2025 Not Ready for Inspection ENRIQUE MIRELES
Final 7/21/2025 Not Ready for Inspection BRENDAN MORELLI
Service/Power Release 7/21/2025 Not Ready for Inspection BRENDAN MORELLI