1719 1/2 N EDGEMONT ST 90027
Certificate Information: 1719 1/2 N EDGEMONT ST 90027
- Application / Permit
- 21010-30000-04403
- Plan Check / Job No.
- B21WL03794
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story detached ADU (796 sf) with att. 1-car garage and storage (444 sf) and roof deck serving ADU per LAMC 12.22A33 (c) and (d)
- Permit Issued
- Issued on 12/21/2023
- Issuing Office
- San Pedro
- Current Status
- Issued on 12/21/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 10/15/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 10/28/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 5/31/2022 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Plan Check Approved | 1/18/2023 | REZA HAGHIGHAT |
| Issued | 12/21/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2022 | ABEL CASILLAS |
| Tenant Habitability Plan | Cleared | 5/4/2022 | MICHAEL SOTO |
| Hydrant and Access approval | Cleared | 6/1/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 10/24/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 10/24/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 10/26/2022 | ABEL CASILLAS |
| ZI | Cleared | 12/7/2022 | LIKYELESH ABERA |
| Grading Pre-Inspection | Cleared | 1/18/2023 | FELIPE HERNANDEZ |
Contact Information
| Contractor | Cunanan Voltaire; Lic. No.: 973248-B | 22418 RAVENNA AVENUE CARSON, CA 90745 |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: C53875 | 460 E CARSON PLAZA DR STE 212 CARSON, CA 90746 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/4/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/5/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/11/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/10/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 4/10/2024 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 4/10/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/24/2024 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 4/26/2024 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 5/7/2024 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 5/13/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/19/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/19/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 8/21/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/26/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 11/13/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 11/13/2024 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 11/13/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 11/15/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 11/15/2024 | Approved | BRENDAN MORELLI |
| Final | 3/25/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 3/25/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 3/25/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 3/25/2025 | Approved | ENRIQUE MIRELES |
| Final | 4/15/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 4/15/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 7/21/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Service/Power Release | 7/21/2025 | Not Ready for Inspection | BRENDAN MORELLI |