9954 N VENA AVE 91331

Certificate Information: 9954 N VENA AVE 91331

Application / Permit
21010-30000-04322
Plan Check / Job No.
B21WL03745
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADU PER LAMC 12.22 A.33(c) AND (d). "COMPLY WITH DEPARTMENT ORDER effective date 05/03/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 3/4/2022
Issuing Office
Current Status
CofO Issued on 1/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 KAVIAN REFAHI
Corrections Issued 8/28/2021 KAVIAN REFAHI
Applicant returned to address corrections 1/27/2022 MARJAN SHENASI
Plan Check Approved 2/15/2022 MARJAN SHENASI
Issued 3/4/2022 APPLICANT
Building Plans Picked Up 3/14/2022 APPLICANT
CofO in Progress 12/2/2022 ARAM AVEDISIAN
Permit Finaled 1/14/2023 MICHAEL SMITH
CofO Issued 1/14/2023 MICHAEL SMITH
Permit Finaled 1/14/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/22/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/23/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/23/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 11/24/2021 RIDWAN HARDY
Low Impact Development Cleared 1/4/2022 CHRIS PARK
Roof/Waste drainage to street Cleared 1/5/2022 JOHN LIN
Hydrant and Access approval Cleared 1/11/2022 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/18/2022 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 5/18/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 5/18/2022 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 5/20/2022 Conditional Approval MICHEL ABAJAN
METHANE-Subgrade 5/20/2022 Conditional Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/16/2022 Partial Approval MICHEL ABAJAN
Insulation 6/16/2022 Partial Approval MICHEL ABAJAN
Gas Test 6/22/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 6/22/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 7/15/2022 Partial Inspection MICHEL ABAJAN
Green Building Rough 7/15/2022 Partial Inspection MICHEL ABAJAN
MERV13>=Rough 7/15/2022 Approved MICHEL ABAJAN
METHANE-Rough 7/15/2022 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 7/15/2022 Partial Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 7/15/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/28/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/28/2022 Approved MICHEL ABAJAN
Green Building Rough 7/28/2022 Approved MICHEL ABAJAN
HVAC-Rough 7/28/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 7/28/2022 Approved MICHEL ABAJAN
Underground Mechanical 7/28/2022 Approved MICHEL ABAJAN
Insulation 8/3/2022 Conditional Approval MICHEL ABAJAN
Interior/Exterior Lathing 8/3/2022 Approved MICHEL ABAJAN
Drywall Nailing 8/11/2022 Corrections Issued MISAEL ESPARZA
Drywall Nailing 8/15/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/24/2022 Approved ASHLEY THOMPSON
Shower Pan 8/24/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Final 11/7/2022 Approved MICHEL ABAJAN
Final 11/7/2022 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 11/7/2022 Approved MICHEL ABAJAN
Green Building Final 11/7/2022 Approved MICHEL ABAJAN
HVAC-Final 11/7/2022 Approved MICHEL ABAJAN
MERV13>=Final 11/7/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 11/7/2022 Approved MICHEL ABAJAN
PLUMBING-Final 11/7/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved MICHEL ABAJAN
Service/Power Release 11/7/2022 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 11/7/2022 Approved MICHEL ABAJAN
Final 11/10/2022 Corrections Issued MICHEL ABAJAN
Service/Power Release 11/10/2022 Not Ready for Inspection MICHEL ABAJAN
Final 12/2/2022 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 12/2/2022 Approved ARAM AVEDISIAN