12447 W MILTON ST 90066

Certificate Information: 12447 W MILTON ST 90066

Application / Permit
21010-30000-04128
Plan Check / Job No.
B21WL03621
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
******Assign to same plan checker as B21WL03620******* new 2-story house *** 1 of 2 ***
Permit Issued
Issued on 1/31/2022
Issuing Office
Current Status
CofO Issued on 3/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 FELIPE HERNANDEZ
Corrections Issued 9/7/2021 FELIPE HERNANDEZ
Quality Review Completed 9/16/2021 TARIK SAOUD
Plan Check Approved 1/24/2022 FELIPE HERNANDEZ
Issued 1/31/2022 APPLICANT
Building Plans Picked Up 2/1/2022 APPLICANT
CofO in Progress 3/29/2023 HERBERT GIRON
Permit Finaled 3/31/2023 DANIEL ORRANTE
CofO Issued 3/31/2023 DANIEL ORRANTE
Permit Finaled 3/31/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 9/9/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/14/2021 DINAH GARIN
Sewer availability Cleared 9/14/2021 DINAH GARIN
Low Impact Development Cleared 9/22/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/22/2021 DINAH GARIN
Specific Plan Cleared 10/4/2021 PETE EYRE
Trees in Parkway Cleared 10/28/2021 ADALBERTO VERA
Hydrant and Access approval Cleared 12/6/2021 GILBERT URREA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Zepeda General Building; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/24/2022 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/12/2022 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 4/12/2022 Approved JESUS RODRIGUEZ
Special/Order Compliance 4/12/2022 Partial Inspection MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/13/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 5/19/2022 Conditional Approval STEPHANIE SWANSON
Deputy Wood Construction 7/18/2022 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 7/28/2022 Approved HERBERT GIRON
HVAC-Rough 7/28/2022 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Conditional Approval HERBERT GIRON
Wood Frame 8/1/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 8/8/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 8/8/2022 Corrections Issued HERBERT GIRON
HVAC-Rough 8/10/2022 Approved HERBERT GIRON
PLUMBING-Rough 8/10/2022 Approved HERBERT GIRON
Insulation 8/15/2022 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 8/15/2022 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 8/17/2022 Approved HERBERT GIRON
Green Building Rough 8/17/2022 Approved HERBERT GIRON
MERV13>=Rough 8/17/2022 Approved HERBERT GIRON
Verify Sprinkler Sign Off 8/17/2022 Approved HERBERT GIRON
Insulation 8/22/2022 Approved HERBERT GIRON
Drywall Nailing 8/30/2022 Approved HERBERT GIRON
Shower Pan 9/12/2022 Not Ready for Inspection HERBERT GIRON
Shower Pan 9/13/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 9/30/2022 Approved HERBERT GIRON
ELECTRICAL-Final 2/24/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Final 2/24/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 2/24/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 3/1/2023 Corrections Issued HERBERT GIRON
Gas Test 3/1/2023 Corrections Issued HERBERT GIRON
HVAC-Final 3/1/2023 Approved HERBERT GIRON
PLUMBING-Final 3/1/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 3/3/2023 Not Ready for Inspection HERBERT GIRON
Final 3/3/2023 Corrections Issued HERBERT GIRON
Gas Test 3/3/2023 Approved HERBERT GIRON
Green Building Final 3/3/2023 Approved HERBERT GIRON
MERV13>=Final 3/3/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/3/2023 SGSOV Not Ready HERBERT GIRON
Service/Power Release 3/3/2023 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 3/3/2023 Approved HERBERT GIRON
ELECTRICAL-Final 3/7/2023 Conditional Approval HERBERT GIRON
PLUMBING-Final 3/7/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved HERBERT GIRON
ELECTRICAL-Final 3/13/2023 Approved HERBERT GIRON
Final 3/13/2023 Corrections Issued HERBERT GIRON
Final 3/28/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 3/28/2023 Approved HERBERT GIRON