2469 N WESTRIDGE ROAD 90049

Certificate Information: 2469 N WESTRIDGE ROAD 90049

Application / Permit
21010-30000-04057
Plan Check / Job No.
B21WL03556
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (39'x 22') DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2 (e) (1) (B) and LAMC 12.22 A.33 (c) (d) and (g), NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 4/4/2022
Issuing Office
Current Status
CofO Issued on 5/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 TROY DEGUZMAN
Corrections Issued 9/1/2021 TROY DEGUZMAN
Quality Review Completed 9/2/2021 OMID HEDAYAT
Applicant returned to address corrections 2/17/2022 TROY DEGUZMAN
Applicant returned to address corrections 3/5/2022 RICHARD GARCIA
Applicant returned to address corrections 3/18/2022 TROY DEGUZMAN
Plan Check Approved 3/25/2022 TROY DEGUZMAN
Issued 4/4/2022 APPLICANT
CofO in Progress 5/6/2025 KEVIN SARGSYAN
Permit Finaled 5/14/2025 RICHARD STEINBACH
CofO Issued 5/14/2025 RICHARD STEINBACH
Permit Finaled 5/14/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/8/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 10/8/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 10/8/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 10/8/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 10/8/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 10/8/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 10/8/2021 SAUL GARCIA
Sewer availability Cleared 10/8/2021 SAUL GARCIA
Watercourse Cleared 10/8/2021 SAUL GARCIA
Roof/Waste drainage to street Cleared 10/14/2021 SAUL GARCIA
Hydrant and Access approval Cleared 10/22/2021 KURT CORRAL
Low Impact Development Cleared 2/2/2022 ORVAL HERNANDEZ-MARCI
GPI Written Notices Cleared 2/17/2022 VASIL MIHALEV
Grading Pre-Inspection Cleared 2/17/2022 VASIL MIHALEV
Green Code Cleared 2/17/2022 TROY DEGUZMAN

Contact Information

Architect Dewan,, Steven Mark; Lic. No.: C24577 439 BROADWAY      COSTA MESA, CA 92627
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/18/2022 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 8/25/2022 Partial Inspection JUAN VALENZUELA
Underground Mechanical 8/25/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/31/2022 Corrections Issued KENNETH NAGLE
Footing/Foundation/Slab 9/1/2022 Corrections Issued KENNETH NAGLE
Pre-Inspection 9/15/2022 Partial Inspection JUAN VALENZUELA
Footing/Foundation/Slab 11/17/2022 Corrections Issued JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 1/23/2023 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 1/23/2023 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/22/2023 No Access for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 2/22/2023 No Access for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 3/8/2023 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Corrections Issued KEVIN SARGSYAN
Deputy Wood Construction 12/13/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/19/2023 No Access for Inspection KEVIN SARGSYAN
Deputy Wood Construction 1/4/2024 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Partial Approval KEVIN SARGSYAN
HVAC-Rough 1/12/2024 No Access for Inspection KEVIN SARGSYAN
HVAC-Rough 1/16/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/17/2024 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 1/19/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/23/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/1/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 2/7/2024 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 2/8/2024 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 2/9/2024 Partial Approval KEVIN SARGSYAN
HVAC-Rough 2/12/2024 Corrections Issued KEVIN SARGSYAN
Shower Pan 3/7/2024 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 3/11/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 3/12/2024 Approved KEVIN SARGSYAN
HVAC-Rough 3/20/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/21/2024 Corrections Issued KEVIN SARGSYAN
FLOOD-Proofing Certificate 3/21/2024 Approved KEVIN SARGSYAN
Green Building Rough 3/21/2024 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 3/21/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/22/2024 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 3/28/2024 Approved KEVIN SARGSYAN
Insulation 4/10/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 4/11/2024 Not Ready for Inspection KEVIN SARGSYAN
Drywall Nailing 4/23/2024 Approved KEVIN SARGSYAN
Special/Order Compliance 5/10/2024 Partial Inspection KEVIN SARGSYAN
Gas Test 5/21/2024 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 5/21/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 5/24/2024 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 6/10/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 11/19/2024 No Access for Inspection KEVIN SARGSYAN
PLUMBING-Final 11/22/2024 No Access for Inspection KEVIN SARGSYAN
Service/Power Release 12/3/2024 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 12/9/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 12/12/2024 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 12/12/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 12/12/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 12/18/2024 Approved KEVIN SARGSYAN
HVAC-Final 1/23/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Final 1/29/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Final 2/25/2025 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 3/3/2025 Approved KEVIN SARGSYAN
Special/Order Compliance 3/11/2025 Partial Inspection KEVIN SARGSYAN
Final 4/18/2025 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/18/2025 Approved KEVIN SARGSYAN
Green Building Final 4/18/2025 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 4/18/2025 Not Required KEVIN SARGSYAN
Smoke Detectors 4/18/2025 Approved KEVIN SARGSYAN
Final 5/1/2025 Conditional Approval KEVIN SARGSYAN
Final 5/2/2025 Not Ready for Inspection KEVIN SARGSYAN
Final 5/6/2025 OK to Issue CofO KEVIN SARGSYAN