13757 W RAYWOOD DR 90049
Certificate Information: 13757 W RAYWOOD DR 90049
- Application / Permit
- 21010-30000-04056
- Plan Check / Job No.
- B21WL03556
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (61'-0"x 41'-4") IRR SHAPE TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, NFPA-13D AUTOMATIC FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/4/2022
- Issuing Office
- Current Status
- CofO Issued on 5/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | TROY DEGUZMAN |
| Corrections Issued | 9/1/2021 | TROY DEGUZMAN |
| Quality Review Completed | 9/2/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/17/2022 | TROY DEGUZMAN |
| Applicant returned to address corrections | 3/5/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 3/18/2022 | TROY DEGUZMAN |
| Plan Check Approved | 3/25/2022 | TROY DEGUZMAN |
| Issued | 4/4/2022 | APPLICANT |
| CofO in Progress | 5/6/2025 | KEVIN SARGSYAN |
| Permit Finaled | 5/14/2025 | RICHARD STEINBACH |
| CofO Issued | 5/14/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/14/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2021 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 10/8/2021 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 10/8/2021 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 10/8/2021 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 10/8/2021 | SAUL GARCIA |
| BHO/Hillside ordinance | Cleared | 10/8/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2021 | SAUL GARCIA |
| Permit | Cleared | 10/8/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 10/8/2021 | SAUL GARCIA |
| Watercourse | Cleared | 10/8/2021 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 10/14/2021 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 10/22/2021 | KURT CORRAL |
| Trees in Parkway | Cleared | 11/23/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 2/2/2022 | ORVAL HERNANDEZ-MARCI |
| GPI Written Notices | Cleared | 2/17/2022 | VASIL MIHALEV |
| Grading Pre-Inspection | Cleared | 2/17/2022 | VASIL MIHALEV |
| Green Code | Cleared | 2/17/2022 | TROY DEGUZMAN |
Contact Information
| Architect | Dewan,, Steven Mark; Lic. No.: C24577 | 439 BROADWAY COSTA MESA, CA 92627 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/13/2022 | Partial Inspection | JUAN VALENZUELA |
| Underground Mechanical | 7/27/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/25/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/31/2022 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 9/1/2022 | Corrections Issued | KENNETH NAGLE |
| Pre-Inspection | 9/15/2022 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 10/7/2022 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 10/7/2022 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/17/2022 | Corrections Issued | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 1/23/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 1/23/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/22/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Pre-Inspection | 9/6/2023 | Partial Inspection | KENNETH NAGLE |
| Special/Order Compliance | 9/6/2023 | Partial Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 10/20/2023 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/23/2023 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/1/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Wood Construction | 11/17/2023 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 12/18/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 1/12/2024 | No Access for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 1/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/17/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/23/2024 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/8/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/9/2024 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 2/12/2024 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 3/7/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 3/11/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/12/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 3/20/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/21/2024 | Corrections Issued | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 3/21/2024 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 3/21/2024 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 3/21/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/22/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/28/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/1/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/4/2024 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 4/10/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/12/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 4/23/2024 | Approved | KEVIN SARGSYAN |
| Special/Order Compliance | 5/10/2024 | Partial Inspection | KEVIN SARGSYAN |
| Gas Test | 5/21/2024 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/21/2024 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/24/2024 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/10/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 11/19/2024 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 11/22/2024 | No Access for Inspection | KEVIN SARGSYAN |
| Service/Power Release | 12/3/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 12/9/2024 | Corrections Issued | KEVIN SARGSYAN |
| Service/Power Release | 12/9/2024 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 12/12/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 12/12/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 12/12/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/18/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 1/23/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 1/29/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 2/25/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 3/3/2025 | Approved | KEVIN SARGSYAN |
| Special/Order Compliance | 3/11/2025 | Partial Inspection | KEVIN SARGSYAN |
| Final | 4/18/2025 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 4/18/2025 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 4/18/2025 | Approved | KEVIN SARGSYAN |
| Final | 5/1/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 5/2/2025 | Corrections Issued | KEVIN SARGSYAN |
| Final | 5/6/2025 | OK to Issue CofO | KEVIN SARGSYAN |