2713-2715 S MCCONNELL DR 90064

Certificate Information: 2713-2715 S MCCONNELL DR 90064

Application / Permit
21010-30000-04054
Plan Check / Job No.
B21WL03554
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story S.F.D. with basement, 3-car garage, and attached ADU. PER LAMC 12.22 A.33 (c) and (e)
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
CofO Issued on 10/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 ALFREDO JARA
Corrections Issued 9/1/2021 ALFREDO JARA
Quality Review Completed 9/13/2021 TARIK SAOUD
Applicant returned to address corrections 3/21/2022 ALFREDO JARA
Applicant returned to address corrections 5/3/2022 ALFREDO JARA
Applicant returned to address corrections 6/14/2022 ALFREDO JARA
Applicant returned to address corrections 6/30/2022 ALFREDO JARA
Plan Check Approved 7/5/2022 ALFREDO JARA
Building Plans Picked Up 7/7/2022 APPLICANT
Issued 7/18/2022 APPLICANT
CofO in Progress 10/15/2025 ASHLEY THOMPSON
Permit Finaled 10/16/2025 RICHARD STEINBACH
CofO Issued 10/16/2025 RICHARD STEINBACH
Permit Finaled 10/16/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/5/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/26/2021 DINAH GARIN
Sewer availability Cleared 10/26/2021 DINAH GARIN
Specific Plan Cleared 12/13/2021 FREDDY GARCIA
Hydrant and Access approval Cleared 12/28/2021 GILBERT URREA
Low Impact Development Cleared 4/7/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 4/12/2022 DINAH GARIN
Excavation more than 5-ft deep Cleared 5/4/2022 CALOSHA APPROVED
GPI Written Notices Cleared 5/4/2022 ALFREDO JARA
Grading Pre-Inspection Cleared 5/4/2022 ALFREDO JARA

Contact Information

Contractor Sunset Built Inc; Lic. No.: 1005054-B 8383 WILSHIRE BLVD #800      BEVERLY HILLS, CA 90211
Engineer Resnick,, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025
Engineer Sayah,, Daniel H; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/23/2022 Partial Approval OGANES TARAKHCHYAN
METHANE-Subgrade 9/16/2022 Approved ANDREW NAVE
Underground Mechanical 10/14/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Other (see comments) 10/26/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 11/2/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/3/2022 Partial Approval OGANES TARAKHCHYAN
METHANE-Barrier 11/3/2022 Approved OGANES TARAKHCHYAN
Deputy Reinf. Concrete 11/7/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Other (see comments) 11/23/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/28/2022 Partial Approval OGANES TARAKHCHYAN
Reinforced Concrete Frame 11/28/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Other (see comments) 12/13/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/14/2022 Partial Approval STEPHANIE SWANSON
Deputy Reinf. Concrete 12/15/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 3/9/2023 Conditional Approval ASHLEY THOMPSON
Deputy Drilled-In Anchors 3/28/2023 Conditional Approval DAVID FEILER
Deputy Steel/Welding 4/13/2023 Conditional Approval ASHLEY THOMPSON
Deputy Steel/Welding 4/14/2023 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 4/20/2023 Partial Approval CLAYTON GRAHAM
Deputy Reinf. Concrete 4/21/2023 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 4/27/2023 Conditional Approval CLAYTON GRAHAM
METHANE-Subgrade 4/27/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Partial Approval CLAYTON GRAHAM
Deputy Other (see comments) 5/10/2023 Conditional Approval CLAYTON GRAHAM
Footing/Foundation/Slab 5/11/2023 Partial Approval CLAYTON GRAHAM
Deputy Steel/Welding 5/12/2023 Conditional Approval CLAYTON GRAHAM
Deputy Reinf. Concrete 5/15/2023 Conditional Approval CLAYTON GRAHAM
Deputy Steel/Welding 5/15/2023 Conditional Approval CLAYTON GRAHAM
Deputy Reinf. Concrete 5/17/2023 Conditional Approval CLAYTON GRAHAM
Deputy Steel/Welding 5/31/2023 Conditional Approval CLAYTON GRAHAM
Deputy Drilled-In Anchors 6/2/2023 Conditional Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Partial Approval JEREMY TODD
Footing/Foundation/Slab 9/6/2023 Not Ready for Inspection CLAYTON GRAHAM
METHANE-Subgrade 9/6/2023 Not Ready for Inspection CLAYTON GRAHAM
Deputy Reinf. Concrete 9/14/2023 Conditional Approval CLAYTON GRAHAM
HVAC-Rough 12/7/2023 Corrections Issued MICHAEL PELHAM
PLUMBING-Rough 12/7/2023 Corrections Issued MICHAEL PELHAM
Sewer 12/7/2023 Approved MICHAEL PELHAM
HVAC-Rough 12/13/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/13/2023 Partial Approval OGANES TARAKHCHYAN
Shower Pan 12/13/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/15/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Approved OGANES TARAKHCHYAN
METHANE-Rough 2/22/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/21/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Rough 3/21/2024 Corrections Issued OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 3/21/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/5/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 4/5/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/5/2024 Partial Approval OGANES TARAKHCHYAN
Insulation 4/12/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/30/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/8/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 4/4/2025 Not Ready for Inspection ASHLEY THOMPSON
Underground Mechanical 4/4/2025 Partial Approval ASHLEY THOMPSON
HVAC-Final 4/23/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Final 5/7/2025 Conditional Approval MEL KHACHATOURIAN
HVAC-Final 5/14/2025 Approved ASHLEY THOMPSON
PLUMBING-Final 5/27/2025 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 6/6/2025 Conditional Approval BOBBY KEY
PLUMBING-Final 6/6/2025 Approved BOBBY KEY
ELECTRICAL-Final 6/18/2025 Approved ASHLEY THOMPSON
Service/Power Release 6/18/2025 Approved ASHLEY THOMPSON
Final 10/3/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 10/3/2025 Approved ASHLEY THOMPSON
Green Building Final 10/3/2025 Approved ASHLEY THOMPSON
METHANE-Subgrade 10/3/2025 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 10/3/2025 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 10/3/2025 Corrections Issued ASHLEY THOMPSON
Final 10/14/2025 OK to Issue CofO ASHLEY THOMPSON
Smoke Detectors 10/14/2025 Approved ASHLEY THOMPSON