2713-2715 S MCCONNELL DR 90064
Certificate Information: 2713-2715 S MCCONNELL DR 90064
- Application / Permit
- 21010-30000-04054
- Plan Check / Job No.
- B21WL03554
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-story S.F.D. with basement, 3-car garage, and attached ADU. PER LAMC 12.22 A.33 (c) and (e)
- Permit Issued
- Issued on 7/18/2022
- Issuing Office
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | ALFREDO JARA |
| Corrections Issued | 9/1/2021 | ALFREDO JARA |
| Quality Review Completed | 9/13/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 3/21/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 5/3/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 6/14/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 6/30/2022 | ALFREDO JARA |
| Plan Check Approved | 7/5/2022 | ALFREDO JARA |
| Building Plans Picked Up | 7/7/2022 | APPLICANT |
| Issued | 7/18/2022 | APPLICANT |
| CofO in Progress | 10/15/2025 | ASHLEY THOMPSON |
| Permit Finaled | 10/16/2025 | RICHARD STEINBACH |
| CofO Issued | 10/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2021 | DINAH GARIN |
| Sewer availability | Cleared | 10/26/2021 | DINAH GARIN |
| Specific Plan | Cleared | 12/13/2021 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 12/28/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 4/7/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/12/2022 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 5/4/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/4/2022 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 5/4/2022 | ALFREDO JARA |
Contact Information
| Contractor | Sunset Built Inc; Lic. No.: 1005054-B | 8383 WILSHIRE BLVD #800 BEVERLY HILLS, CA 90211 |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/23/2022 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 9/16/2022 | Approved | ANDREW NAVE |
| Underground Mechanical | 10/14/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Other (see comments) | 10/26/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 11/2/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/3/2022 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Barrier | 11/3/2022 | Approved | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 11/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Other (see comments) | 11/23/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/28/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Reinforced Concrete Frame | 11/28/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Other (see comments) | 12/13/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/14/2022 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 12/15/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/9/2023 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Drilled-In Anchors | 3/28/2023 | Conditional Approval | DAVID FEILER |
| Deputy Steel/Welding | 4/13/2023 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Steel/Welding | 4/14/2023 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 4/20/2023 | Partial Approval | CLAYTON GRAHAM |
| Deputy Reinf. Concrete | 4/21/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 4/27/2023 | Conditional Approval | CLAYTON GRAHAM |
| METHANE-Subgrade | 4/27/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Partial Approval | CLAYTON GRAHAM |
| Deputy Other (see comments) | 5/10/2023 | Conditional Approval | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 5/11/2023 | Partial Approval | CLAYTON GRAHAM |
| Deputy Steel/Welding | 5/12/2023 | Conditional Approval | CLAYTON GRAHAM |
| Deputy Reinf. Concrete | 5/15/2023 | Conditional Approval | CLAYTON GRAHAM |
| Deputy Steel/Welding | 5/15/2023 | Conditional Approval | CLAYTON GRAHAM |
| Deputy Reinf. Concrete | 5/17/2023 | Conditional Approval | CLAYTON GRAHAM |
| Deputy Steel/Welding | 5/31/2023 | Conditional Approval | CLAYTON GRAHAM |
| Deputy Drilled-In Anchors | 6/2/2023 | Conditional Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Partial Approval | JEREMY TODD |
| Footing/Foundation/Slab | 9/6/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| METHANE-Subgrade | 9/6/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Deputy Reinf. Concrete | 9/14/2023 | Conditional Approval | CLAYTON GRAHAM |
| HVAC-Rough | 12/7/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 12/7/2023 | Corrections Issued | MICHAEL PELHAM |
| Sewer | 12/7/2023 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 12/13/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/13/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 12/13/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/15/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 2/22/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/21/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Rough | 3/21/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 3/21/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/5/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 4/5/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/5/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 4/12/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/30/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/8/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 4/4/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Underground Mechanical | 4/4/2025 | Partial Approval | ASHLEY THOMPSON |
| HVAC-Final | 4/23/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 5/7/2025 | Conditional Approval | MEL KHACHATOURIAN |
| HVAC-Final | 5/14/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 5/27/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 6/6/2025 | Conditional Approval | BOBBY KEY |
| PLUMBING-Final | 6/6/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/18/2025 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 6/18/2025 | Approved | ASHLEY THOMPSON |
| Final | 10/3/2025 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 10/3/2025 | Approved | ASHLEY THOMPSON |
| Green Building Final | 10/3/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 10/3/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 10/3/2025 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 10/3/2025 | Corrections Issued | ASHLEY THOMPSON |
| Final | 10/14/2025 | OK to Issue CofO | ASHLEY THOMPSON |
| Smoke Detectors | 10/14/2025 | Approved | ASHLEY THOMPSON |