312 N EAST RUSTIC ROAD 90402
Certificate Information: 312 N EAST RUSTIC ROAD 90402
- Application / Permit
- 21010-30000-04045
- Plan Check / Job No.
- B21WL03542
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new two story single family home with attached garage
- Permit Issued
- Issued on 9/29/2022
- Issuing Office
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | TARIK SAOUD |
| Corrections Issued | 8/31/2021 | TARIK SAOUD |
| Quality Review Completed | 9/1/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 9/14/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 9/29/2022 | CHIHARU SUZUKI |
| Issued | 9/29/2022 | APPLICANT |
| Building Plans Picked Up | 9/30/2022 | APPLICANT |
| CofO in Progress | 11/21/2024 | ARAM AVEDISIAN |
| CofO Issued | 11/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/22/2021 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 9/22/2021 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 9/22/2021 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 9/22/2021 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 9/22/2021 | KATHLEEN LEE |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | KATHLEEN LEE |
| Permit | Cleared | 9/22/2021 | KATHLEEN LEE |
| Sewer availability | Cleared | 9/22/2021 | KATHLEEN LEE |
| Low Impact Development | Cleared | 10/1/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/28/2021 | KATHLEEN LEE |
| Trees in Parkway | Cleared | 10/30/2021 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 11/5/2021 | JOHN CONNEALLY |
| Coastal Zone | Cleared | 8/19/2022 | YINGSHI HUANG |
| Grading Pre-Inspection | Cleared | 9/14/2022 | TARIK SAOUD |
Contact Information
| Architect | Blumenberg,, Richard Leo; Lic. No.: C10862 | 15200 SUNSET BLVD STE 201 PACIFIC PALISADES, CA 90272 |
| Contractor | Owner-Builder | , |
| Engineer | Bains,, Gagan Prit Singh; Lic. No.: S4482 | 222 E HUNTINGTON DR STE 235 MONROVIA, CA 91016 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/15/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/15/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/15/2022 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/18/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/28/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Other (see comments) | 12/2/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 12/14/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 12/15/2022 | Approved | KEVIN SARGSYAN |
| Deputy Steel/Welding | 12/28/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 8/11/2023 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 8/16/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/16/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 8/18/2023 | Corrections Issued | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 8/18/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/11/2023 | Partial Approval | OGANES TARAKHCHYAN |
| FLOOD-Proofing Certificate | 9/11/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/11/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 9/22/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/22/2023 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/26/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/3/2023 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 10/3/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/6/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/10/2024 | Approved | JESUS RODRIGUEZ |
| Gas Test | 9/10/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/10/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 9/10/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Final | 11/20/2024 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 11/20/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 11/20/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 11/20/2024 | Approved | ARAM AVEDISIAN |
| Final | 11/21/2024 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 11/21/2024 | Approved | ARAM AVEDISIAN |