839 N MCCADDEN PL unit A-C 90038

Certificate Information: 839 N MCCADDEN PL unit A-C 90038

Application / Permit
21010-30000-04014
Plan Check / Job No.
B21WL03516
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
new Duplex w/ ADU per state law (front building)
Permit Issued
Issued on 5/9/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 TARIK SAOUD
Corrections Issued 8/31/2021 TARIK SAOUD
Quality Review Completed 9/1/2021 CHIHARU SUZUKI
Applicant returned to address corrections 4/1/2022 TARIK SAOUD
Plan Check Approved 4/27/2022 TARIK SAOUD
Issued 5/9/2022 APPLICANT
Building Plans Picked Up 6/3/2022 APPLICANT
CofO in Progress 10/30/2023 BRIAN SULLIVAN
CofO Issued 11/2/2023 DEROLD HAUFF
Permit Finaled 11/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/4/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 9/10/2021 CECILIO NAVARRO
Sewer availability Cleared 9/10/2021 CECILIO NAVARRO
Frnt yard landscape/Water mgmt Cleared 11/16/2021 RUBEN VASQUEZ
Hydrant and Access approval Cleared 11/30/2021 JOHN CONNEALLY
Low Impact Development Cleared 1/28/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 2/3/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/27/2022 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/5/2022 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 9/8/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Conditional Approval JOAQUIN GREENOUGH
PLUMBING-Rough 9/30/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 9/30/2022 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 10/4/2022 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 10/7/2022 Approved JOSE AVILA
Underground Mechanical 10/11/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Wood Construction 10/20/2022 Conditional Approval JOAQUIN GREENOUGH
PLUMBING-Rough 10/21/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 11/9/2022 No Access for Inspection JOAQUIN GREENOUGH
HVAC-Rough 11/16/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 11/16/2022 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 11/22/2022 Partial Approval BRIAN SULLIVAN
Shower Pan 11/22/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 11/29/2022 Approved BRIAN SULLIVAN
Green Building Rough 11/29/2022 Approved BRIAN SULLIVAN
METHANE-Rough 11/29/2022 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 11/29/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 12/22/2022 Approved BRIAN SULLIVAN
Insulation 12/30/2022 Approved STUART CHAPMAN
Drywall Nailing 1/17/2023 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 6/30/2023 Corrections Issued BRIAN SULLIVAN
HVAC-Final 6/30/2023 Corrections Issued BRIAN SULLIVAN
PLUMBING-Final 6/30/2023 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Final 7/17/2023 Approved BRIAN SULLIVAN
HVAC-Final 7/17/2023 Approved BRIAN SULLIVAN
PLUMBING-Final 7/17/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Final 8/17/2023 Approved JOAQUIN GREENOUGH
Service/Power Release 8/17/2023 Approved JOAQUIN GREENOUGH
Final 9/1/2023 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 9/1/2023 Approved BRIAN SULLIVAN
Green Building Final 9/1/2023 Approved BRIAN SULLIVAN
METHANE-Barrier 9/1/2023 Approved BRIAN SULLIVAN
METHANE-Subgrade 9/1/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 9/1/2023 Approved BRIAN SULLIVAN
Final 10/30/2023 OK to Issue CofO BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 10/30/2023 SGSOV Approved BRIAN SULLIVAN