839 N MCCADDEN PL unit A-C 90038
Certificate Information: 839 N MCCADDEN PL unit A-C 90038
- Application / Permit
- 21010-30000-04014
- Plan Check / Job No.
- B21WL03516
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- new Duplex w/ ADU per state law (front building)
- Permit Issued
- Issued on 5/9/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | TARIK SAOUD |
| Corrections Issued | 8/31/2021 | TARIK SAOUD |
| Quality Review Completed | 9/1/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 4/1/2022 | TARIK SAOUD |
| Plan Check Approved | 4/27/2022 | TARIK SAOUD |
| Issued | 5/9/2022 | APPLICANT |
| Building Plans Picked Up | 6/3/2022 | APPLICANT |
| CofO in Progress | 10/30/2023 | BRIAN SULLIVAN |
| CofO Issued | 11/2/2023 | DEROLD HAUFF |
| Permit Finaled | 11/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/10/2021 | CECILIO NAVARRO |
| Frnt yard landscape/Water mgmt | Cleared | 11/16/2021 | RUBEN VASQUEZ |
| Hydrant and Access approval | Cleared | 11/30/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 1/28/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 2/3/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/27/2022 | Approved | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 8/5/2022 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/30/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 9/30/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/4/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/7/2022 | Approved | JOSE AVILA |
| Underground Mechanical | 10/11/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 10/20/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/21/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 11/9/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 11/16/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 11/16/2022 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 11/22/2022 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 11/22/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/29/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 11/29/2022 | Approved | BRIAN SULLIVAN |
| METHANE-Rough | 11/29/2022 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 11/29/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 12/22/2022 | Approved | BRIAN SULLIVAN |
| Insulation | 12/30/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 1/17/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 6/30/2023 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Final | 6/30/2023 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Final | 6/30/2023 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Final | 7/17/2023 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 7/17/2023 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 7/17/2023 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/17/2023 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 8/17/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 9/1/2023 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 9/1/2023 | Approved | BRIAN SULLIVAN |
| Green Building Final | 9/1/2023 | Approved | BRIAN SULLIVAN |
| METHANE-Barrier | 9/1/2023 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 9/1/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 9/1/2023 | Approved | BRIAN SULLIVAN |
| Final | 10/30/2023 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Approved | BRIAN SULLIVAN |