5123 S BRYNHURST AVE 90043
Certificate Information: 5123 S BRYNHURST AVE 90043
- Application / Permit
- 21010-30000-03919
- Plan Check / Job No.
- B21WL03432
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- new 2-story ADU 530 sf with attached garage 380 sf. Per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 5/19/2022
- Issuing Office
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | ALFREDO JARA |
| Corrections Issued | 8/24/2021 | ALFREDO JARA |
| Quality Review Completed | 9/2/2021 | TARIK SAOUD |
| Plan Check Approved | 5/3/2022 | ALFREDO JARA |
| Building Plans Picked Up | 5/4/2022 | APPLICANT |
| Issued | 5/19/2022 | APPLICANT |
| CofO in Progress | 5/23/2024 | ANTHONY EGSON |
| CofO Issued | 6/10/2024 | DEROLD HAUFF |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2021 | CELINA MORENO |
| Sewer availability | Cleared | 10/21/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 11/4/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 11/13/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/18/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 6/1/2022 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/6/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 6/6/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/17/2022 | Approved | ANTHONY EGSON |
| Underground Mechanical | 6/17/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/12/2022 | No Access for Inspection | ANTHONY EGSON |
| Green Building Rough | 7/12/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 7/12/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 7/15/2022 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 7/22/2022 | No Access for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/1/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/1/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 8/1/2022 | Partial Approval | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 8/1/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 8/11/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/17/2022 | No Access for Inspection | ANTHONY EGSON |
| HVAC-Rough | 8/17/2022 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 8/17/2022 | No Access for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/24/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 8/24/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 8/24/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 9/1/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 9/1/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 9/1/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/12/2022 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 9/15/2022 | No Access for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/28/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 10/12/2022 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 10/12/2022 | Approved | ANTHONY EGSON |
| Insulation | 10/12/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/12/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/19/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/19/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/31/2023 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 2/14/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/25/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 5/25/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 5/25/2023 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 5/25/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 5/25/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 5/25/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 5/25/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 6/13/2023 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 6/13/2023 | No Access for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 7/5/2023 | Approved | ANTHONY EGSON |
| Gas Test | 7/5/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 7/5/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 7/5/2023 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 7/5/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 8/1/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 8/1/2023 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 8/1/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 8/1/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 9/25/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 9/25/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 9/25/2023 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 9/25/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 9/25/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/21/2024 | Approved | ANTHONY EGSON |
| Final | 3/21/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/21/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 3/21/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/21/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/21/2024 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 3/21/2024 | Approved | ANTHONY EGSON |
| Final | 5/14/2024 | No Access for Inspection | ANTHONY EGSON |
| Green Building Final | 5/14/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 5/22/2024 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 5/22/2024 | Approved | ANTHONY EGSON |
| Service/Power Release | 5/22/2024 | Approved | ANTHONY EGSON |