923 E MILWOOD AVE 90291
Certificate Information: 923 E MILWOOD AVE 90291
- Application / Permit
- 21010-30000-03835
- Plan Check / Job No.
- B21WL03358
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story S.F.D. (3,113 sf) w/ att. garage (394 sf) & roof deck (825 sf)
- Permit Issued
- Issued on 1/3/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | REZA HAGHIGHAT |
| Corrections Issued | 8/16/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 8/26/2021 | TARIK SAOUD |
| Plan Check Approved | 12/5/2024 | REZA HAGHIGHAT |
| Issued | 1/3/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/10/2021 | GILBERT URREA |
| Address approval | Cleared | 7/1/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2024 | DARIN LAM |
| Sewer availability | Cleared | 7/18/2024 | DARIN LAM |
| ZA Case | Cleared | 7/24/2024 | DAVID URITA |
| ZA Case | Cleared | 7/24/2024 | DAVID URITA |
| ZA Case | Cleared | 7/24/2024 | DAVID URITA |
| ZA Case | Cleared | 7/24/2024 | DAVID URITA |
| ZA Case | Cleared | 7/24/2024 | DAVID URITA |
| Specific Plan | Cleared | 8/29/2024 | RICHARD WOO |
| Specific Plan | Cleared | 8/29/2024 | RICHARD WOO |
| Low Impact Development | Cleared | 11/19/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/22/2024 | DARIN LAM |
| Coastal Zone | Cleared | 12/3/2024 | DANIEL CORONADO |
| Specific Plan | Cleared | 12/3/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 12/3/2024 | DANIEL CORONADO |
| ZI | Cleared | 12/3/2024 | DANIEL CORONADO |
Contact Information
| Architect | Daham,, Ramsey Walid; Lic. No.: C34257 | 109 EUCALYPTUS DRIVE EL SEGUNDO, CA 90245 |
| Contractor | Global Developers Inc; Lic. No.: 1023874-B | 152 SOUTH OAKHURST DRIVE 302 BEVERLY HILLS, CA 90212 |
| Engineer | Kim,, Seung Su; Lic. No.: S5909 | 15808 APOLLO PLACE GARDENA, CA 90249 |
| Engineer | Vassallo,, Christopher W; Lic. No.: L8418 | 28441 HIGHRIDGE RD 230 ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/4/2025 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 3/14/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/19/2025 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/19/2025 | Partial Inspection | DAVID FEILER |
| Deputy Steel/Welding | 4/1/2025 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2025 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2025 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 6/23/2025 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 7/2/2025 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/28/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/28/2025 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 8/6/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 8/18/2025 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/21/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/25/2025 | Partial Approval | JAYLIN GRAVITTE |
| Insulation | 8/27/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/27/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/27/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/28/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/29/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/29/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/29/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/8/2025 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 10/1/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 10/7/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/29/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 1/2/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 1/6/2026 | Approved | RUBEN RIVAS |
| Final | 1/16/2026 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 1/16/2026 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Approved | RUBEN RIVAS |
| Service/Power Release | 1/16/2026 | Approved | RUBEN RIVAS |
| Smoke Detectors | 1/16/2026 | Approved | RUBEN RIVAS |
| Final | 4/23/2026 | Partial Approval | RUBEN RIVAS |