714 S MORENO AVE 90049
Certificate Information: 714 S MORENO AVE 90049
- Application / Permit
- 21010-30000-03834
- Plan Check / Job No.
- B21WL03356
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story ADU (576 sf) at rear of the lot per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 12/30/2021
- Issuing Office
- Current Status
- CofO Issued on 10/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | REZA HAGHIGHAT |
| Corrections Issued | 8/13/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 8/26/2021 | TARIK SAOUD |
| Plan Check Approved | 12/16/2021 | REZA HAGHIGHAT |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| Issued | 12/30/2021 | APPLICANT |
| CofO in Progress | 10/4/2023 | MICHAEL PELHAM |
| CofO in Progress | 10/4/2023 | MICHAEL PELHAM |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
| CofO Issued | 10/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/21/2021 | DINAH GARIN |
| Permit | Cleared | 9/21/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | DINAH GARIN |
| Sewer availability | Cleared | 9/22/2021 | DINAH GARIN |
| Specific Plan | Cleared | 10/21/2021 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 11/5/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 11/23/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/8/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/8/2021 | DINAH GARIN |
| Trees in Parkway | Cleared | 12/16/2021 | ADALBERTO VERA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 3/17/2022 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 3/18/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Partial Approval | KENNETH NAGLE |
| Sewer | 7/19/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/20/2022 | Approved | JOHN KIDWELL |
| Underground Mechanical | 7/20/2022 | Conditional Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Corrections Issued | ASHLEY THOMPSON |
| Shower Pan | 11/4/2022 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 11/17/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/29/2022 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/6/2022 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/9/2022 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 12/9/2022 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 12/9/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Wood Frame | 12/9/2022 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/22/2022 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 12/22/2022 | Approved | ASHLEY THOMPSON |
| Insulation | 12/28/2022 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 1/13/2023 | Approved | ASHLEY THOMPSON |
| Insulation | 1/13/2023 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 1/13/2023 | Approved | ASHLEY THOMPSON |
| Gas Test | 7/31/2023 | Approved | MICHAEL PELHAM |
| PLUMBING-Final | 7/31/2023 | Approved | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 9/5/2023 | Approved | JESUS PINEDA |
| Smoke Detectors | 9/5/2023 | Approved | JESUS PINEDA |
| Final | 9/22/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 9/22/2023 | Approved | HERBERT GIRON |
| Green Building Final | 9/22/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 9/22/2023 | Approved | HERBERT GIRON |
| Service/Power Release | 9/22/2023 | Not Ready for Inspection | HERBERT GIRON |
| Final | 9/28/2023 | No Access for Inspection | KENNETH NAGLE |
| HVAC-Final | 9/28/2023 | No Access for Inspection | KENNETH NAGLE |
| Service/Power Release | 9/28/2023 | No Access for Inspection | KENNETH NAGLE |
| Final | 10/3/2023 | OK to Issue CofO | MICHAEL PELHAM |
| HVAC-Final | 10/3/2023 | Approved | MICHAEL PELHAM |
| Service/Power Release | 10/3/2023 | Approved | MICHAEL PELHAM |