11809 W ALLASEBA DR 90066
Certificate Information: 11809 W ALLASEBA DR 90066
- Application / Permit
- 21010-30000-03649
- Plan Check / Job No.
- B21WL03253
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-story s.f.r. w/ att. garage and trusses. Equipped w/fire sprinklres NFPA 13D
- Permit Issued
- Issued on 2/9/2022
- Issuing Office
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | ALFREDO JARA |
| Corrections Issued | 8/9/2021 | ALFREDO JARA |
| Quality Review Completed | 8/23/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 1/3/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 1/4/2022 | ALFREDO JARA |
| Plan Check Approved | 1/5/2022 | ALFREDO JARA |
| Plan Check Approved | 2/9/2022 | ALFREDO JARA |
| Issued | 2/9/2022 | APPLICANT |
| Building Plans Picked Up | 2/11/2022 | APPLICANT |
| CofO in Progress | 4/18/2023 | JOHNNY MIRANDA |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
| CofO Issued | 4/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 8/27/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | DINAH GARIN |
| Sewer availability | Cleared | 8/31/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 10/13/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 10/28/2021 | ADALBERTO VERA |
| Specific Plan | Cleared | 11/17/2021 | VALERIA CEJA |
| Low Impact Development | Cleared | 12/9/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/13/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 1/5/2022 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 1/5/2022 | ALFREDO JARA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/31/2022 | Corrections Issued | JOHNNY MIRANDA |
| Underground Mechanical | 4/4/2022 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 5/9/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 5/9/2022 | Approved | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 5/12/2022 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 7/15/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/15/2022 | Approved | JOHNNY MIRANDA |
| Deputy Wood Construction | 7/20/2022 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 8/12/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/16/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 8/31/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/17/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 10/17/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/17/2022 | Partial Approval | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 10/17/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 10/18/2022 | Not Ready for Inspection | RICHARD STEINBACH |
| Insulation | 10/20/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/20/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 10/20/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Wood Frame | 10/20/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 10/24/2022 | No Access for Inspection | KENNETH NAGLE |
| Interior/Exterior Lathing | 10/24/2022 | No Access for Inspection | KENNETH NAGLE |
| Insulation | 10/31/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 11/9/2022 | Corrections Issued | JOHNNY MIRANDA |
| Shower Pan | 11/14/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 11/17/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 11/21/2022 | Approved | JOHNNY MIRANDA |
| Gas Test | 3/1/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 3/1/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Rec and Parks Fee Memo | 3/1/2023 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 3/9/2023 | Approved | JOHNNY MIRANDA |
| Gas Test | 3/9/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 3/9/2023 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 3/9/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 4/5/2023 | Approved | JOHNNY MIRANDA |
| Final | 4/6/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Final | 4/6/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Smoke Detectors | 4/6/2023 | Approved | CLAYTON GRAHAM |
| Final | 4/12/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 4/12/2023 | Approved | HERBERT GIRON |
| Final | 4/14/2023 | OK to Issue CofO | JOHNNY MIRANDA |